|
|
Second International
Fact-Finding Mission
Baku-Tbilisi-Ceyhan
Pipeline -Turkey Section
March
16th-24th 2003
Human
Rights and Environment Report
6th
May 2003
Campagna
per la Riforma della Banca Mondiale
Kurdish
Human Rights Project
PLATFORM
The
Corner House
CONTENTS
Executive Summary:
A Call for a Moratorium
Background and
Remit of the Mission
The Mission’s
Findings
1 BTC, Security
and Human Rights
1.0 The
Premise of Consultation
1.1 Human
Rights Violations and the Legitimacy of Consultation
1.2 Turkey’s
Human Rights Record
1.3 BTC
and State Repression in the North-East
1.3.1 The
Detention of the Fact-Finding Mission
1.3.2 The
Banning of Newroz
1.3.3 Increased
Detentions and Arrests
1.4 Pipeline
Security and the Gendarmerie
1.5 BTC
and Freedom of Expression
- Consultation
and Disclosure of BTC Project Information
2.0 Summary
of Previous Fact-Finding Mission Findings
2.1 Framework
of Consultation
2.1.1 Environmental
Impact Assessment
2.1.2 Resettlement
Action Plan
2.2 Compliance
with International Standards
2.2.1 Inadequate
Consultation on the EIA and RAP
2.2.2 Inadequate
Consultation of Directly-Affected People
2.3 Flawed
Consultation due to Lack of Freedom of Expression
2.4 Inadequacies
in the Consultation of Women
2.5 Lack
of Consultation on the IGA and HGA
3 Resettlement
and Compensation
3.0 Land
Expropriation, Compensation and the Resettlement Action Plan
3.1 Conflicts
between RAP and HGA
3.2 Deficiencies
in the Implementation of the RAP
3.2.1 Compensating
Customary Landowners and Users
3.2.2 Understanding
of Implementation Arrangements
3.2.3 Negotiation
of Compensation Deals
No Negotiation:
High Transaction Costs
3.2.4 Fairness
of Price
Failure
to Pay Full Replacement Costs: No negotiation for Loss
of Ongoing Productivity: Payments below those budgeted:
Discrimination against users of customarily-owned land:
Engineering consent.
3.2.5 Mechanisms
of Redress
3.2.6 Common
Land and the RAP Fund
3.2.7 Tenants
3.3 Other
Losses Associated with Project
3.4 Failure
to Protect or Enhance Livelihoods
3.5 Inadequate
Consultation with NGOs
3.6 Conclusions
4. Impacts
of the Project on Vulnerable Groups
4.0 Project
Impacts on Minority and Disadvantaged Groups
4.1 The
Application of OD 4.20 to Turkey’s Kurdish Minority
4.1.1 OD
4.20 and Ethnic Minorities
4.1.2 The
Kurds and OD 4.20
4.1.3 Isolation
and Marginalisation
4.2 "Vulnerable
Groups" – A Flawed Approach
4.2.1 Deficiencies
in Policy
4.3 Ethnic
Minorities – Findings of the Fact-Finding Mission
4.3.1 Omissions
and Inadequacies in the RAP
4.3.2 Need
for a Safeguard Measure
4.4 Women
as a Disadvantaged Group
4.5 Religious
Groups
- Corruption
- Conclusions
and Recommendations
6.0 Summary
of Findings
6.01 Systemic
Problems Undermine Legitimacy of Consultation
6.02 Specific
Deficiencies in Consultation and Compensation Procedures
A. Consultation
and Disclosure of Information Flawed
B. Land
Expropriation and Compensation – Legal and Human Rights
Concerns
C Minority
and Disadvantaged Groups
6.1 The
Case for a Moratorium
6.2 Recommendations
A. An
Immediate Moratorium
B. Consideration
of Legal Redress
EXECUTIVE
SUMMARY
CALL
FOR A MORATORIUM ON THE BAKU-TBILISI-CEYHAN PIPELINE PROJECT
This
report constitutes the findings of an international Fact Finding
Mission (FFM) that visited Turkey from 16th-24th
March 2003 to assess the planning and implementation of the proposed
Baku-Tbilisi-Ceyhan (BTC) oil pipeline, which BP and other companies
(as part of the BTC Consortium) intend to build in order to bring
oil from Caspian Sea oilfields to western markets. Funding of the
project will be sought from a number of public bodies, notably the
International Finance Corporation (IFC) of the World Bank Group,
the European Bank for Reconstruction and Development (EBRD) and
a number of western Export Credit Agencies.
The
FFM is the second international fact-finding mission to have visited
the Turkish section of the pipeline. The previous Mission to Turkey
in July 2002 found that the project was in violation of a range
of international standards relating to consultation and resettlement.
It also raised concerns over potential conflicts between the legal
agreements for the project and international human rights and environmental
law.
FINDINGS
OF THE MARCH 2003 FFM
Systemic
and Systematic Abuses
Whilst
the current FFM found that the project developers – the BTC Consortium
or BTC Co. - have taken steps which partially address a number of
the concerns identified by the July 2002 Mission, continuing
violations of international standards on consultation, compensation
and resettlement still characterise the project.
The FFM also identified a number of apparent conflicts between
the Resettlement Action Plan (RAP) for the project and the Turkish
Expropriation Law. Most worrying of all, the FFM found clear-cut
evidence of systemic flaws in the project, arising from the political
context in which the pipeline has been planned and would operate,
that cannot be addressed by piecemeal policy changes.
Systemically,
the FFM found:
- A pattern
of serious and ongoing human rights
abuses in regions through which the pipeline passes, notably in
the north-east, where there has been a
marked recent rise of detentions, arbitrary arrests, surveillance
and harassment by state and military officials;
- A pervasive
atmosphere of repression and lack of freedom of speech in the
region which precludes dissent about the BTC project;
- The strong
likelihood that the human rights situation in the region would
be worsened by the introduction of the pipeline, particularly
due to militarisation via the use of the Gendarmerie (Turkey’s
military police) as the main security force.
Such
abuses were particularly evident in the north-eastern section of
the proposed pipeline route, in Kars and Ardahan provinces,
a region whose population is approximately 30% Kurdish. Here
the Mission found clear-cut evidence of political repression so
systemic as to invalidate the consultation exercises that the project
developers have undertaken. Indeed, the FFM was itself detained
by the Gendarmerie on two occasions and, due to police harassment
and intimidation, was forced to abandon a number of planned visits
to villages affected by the pipeline for fear of exposing local
villagers to potential human rights abuses by the state security
agencies.
These
problems of social context were compounded by an array of specific
deficiencies in the BTC project, including:
- Fundamental
flaws in both the design and the implementation of crucial project
documents like the Environmental Impact Assessment (EIA) and the
Resettlement Action Plan (RAP), including widespread inadequacies
in consultation of appropriate NGOs and social groups;
- Repeated
suggestions that BTC Co. is not carrying out the process of compensation
in the manner claimed. These included allegations of systematically
paying well below market rates for land; imposing rather than
negotiating prices; failing to compensate certain groups of landowners
and users; not providing affected people with proper information
about their rights; and failing to inform them of the many potential
negative impacts of the project. These failures are generating
growing anger among affected people. They are also of particular
concern because BTC has recently written to the Government of
Turkey insisting that BOTAS complete the land acquisition process
as soon as possible - or risk losing the contract;
- The failure
of the project to take sufficient account of the differential
impacts of the pipeline on vulnerable groups, including ethnic
minorities, women and the poor, or to mitigate those problems
appropriately.
The
FFM notes that this catalogue of deficiencies puts the BTC project
in potential conflict with the Turkish Expropriation Law, and hence
also with the Host Government Agreement
reached between BTC Co. and the Turkish Government. It also places
the project in violation of a number of World Bank group’s mandatory
standards, including OD 4.30 (Involuntary Resettlement), and guidelines,
including the IFC Good Practice Manual on Consultation and Disclosure
and IFC Handbook on Preparing a Resettlement Action Plan.
The FFM also finds compelling reasons why OD 4.20 (Indigenous Peoples)
should be applied in order to prevent disproportionately adverse
impacts on ethnic minorities in the region.
In
the FFM’s view, the atmosphere of repression in the north-eastern
region of Turkey – as manifested by arbitrary arrests and detentions,
the inhibition of dissent through police intimidation, and the constant
surveillance of political groups and ordinary people alike by state
security personnel – are such that implementation of the project
to international standards is currently unattainable. Specifically,
such repression renders impossible:
- Credible
consultation with affected communities, in particular minorities
and vulnerable groups, since the pre-condition for credible consultation
– freedom of expression and speech – does not exist;
- Free and
open compensation negotiations by affected landowners and
users as to the payment they receive for the loss of their land;
- Independent
monitoring of the project.
Given
the extent of repression in the north-east, coupled with heightened
tensions over the Kurdish issue in the east of Turkey as whole,
the FFM is also gravely concerned by the human rights implications
of the arrangements for policing the pipeline, should it be built.
Under the legal agreements reached between the Republic of Turkey
and the project developers, the security of the pipeline is the
sole responsibility of the Turkish state – a responsibility that
has been designated to the Gendarmerie, whose record on human rights
has been repeatedly criticised by the Council of Europe. In
the FFM’s view, such arrangements carry high risk of precipitating
human rights abuses, particularly in the north-eastern section of
the pipeline route.
In
such circumstances, the FFM considers that it would be irresponsible
for BTC Co. to proceed with the project unless and until there is
independent confirmation that concerned parties, in particular those
directly affected by the pipeline, are in a position and a socio-cultural
environment to express their views on the project without fear of
reprisal or intimidation and to negotiate freely over compensation
for loss of land and other damages. The FFM also deems it essential
that security concerns arising from the poor human rights record
of Turkey’s security forces be addressed prior to work commencing
on the project.
A
MORATORIUM IS URGENT
Given
the gravity of the situation, the FFM has called for the project
developers and the funding agencies that have been approached for
financial support to impose a Moratorium on the project.
Whilst
many of the deficiencies identified by the FFM (for example, with
regard to levels of compensation) may be remedied by making more
funds available and by taking more time to resolve the outstanding
violations of international standards and potential conflicts with
domestic law, the systemic problems arising from repression in
the region are not amenable to remedial action by either the project
developer or the international financial institutions from which
funding for the project is being sought. There are a number of reasons
for this:
- The World
Bank has no safeguard policies relating to human rights and therefore
no human rights standards that the project must meet if it is
to receive funding. Indeed, the Bank has specifically argued
that its Articles of Agreement, which forbid the Bank from intervening
in the political affairs of client states, preclude the Bank from
adopting any such guidelines since human rights are inherently
"political" issues. Nonetheless, as Ibrahim Shihata,
the former General Counsel of the Bank notes: "Members’ obligations
under the UN Charter prevail over their other treaty obligations,
including their obligations under the Bank’s Articles of Agreement,
by force of an explicit provision in the UN Charter (Article 103).
The Bank itself is bound, by virtue of its Relationship Agreement
with the UN, to take note of the above-mentioned Charter obligations
assumed by its members…." From this legal experts have concluded
that, "the Bank is obliged, as is any other subject of the
law, to ensure that it neither undermines the ability of other
subjects, including its members, to faithfully fulfil their international
obligations nor facilitates or assists violation of those obligations."
In effect, the Bank’s inability to act to address the human
rights concerns identified in this report, coupled with its obligation
to ensure that human rights abuses do not flow from the project
should it be involved, points to its withdrawal until measures
have been taken to remedy the concerns raised as the only viable
option open to it.
- The BTC Consortium
is a private company and, whilst the Host Government Agreement
(HGA) it has signed with Turkey gives it considerable legal powers
over those living in the pipeline corridor, it cannot introduce
the necessary policy reforms that would ensure that Turkish citizens
enjoy the freedom of expression necessary to participate in a
proper consultation on the project or to safeguard their property
rights.
- It is Turkey,
not BTC Co, that is responsible for security, as specified in
the HGA. The project developers therefore have no powers to control
the security provisions and operations for the pipeline without
a renegotiation of the HGA, to which all parties would have to
agree. Nor does the FFM believe that it is in the interests of
project affected people for the project developers to have the
capacity to do so.
In
such circumstances, the FFM believes that a Moratorium on appraising,
financing or building the BTC project constitutes the only legitimate
means available to the International Financial Institutions and
the project developers for ensuring that human rights violations
do not flow from the project. As such, it represents the most responsible
course of action.
Indeed,
in the absence of significant progress being made to address the
repression in the north-east of Turkey, the FFM believes that any
decision by officials of European Union governments to support the
BTC project financially through the World Bank, the EBRD or official
Export Credit Agencies (ECAs) could be open to a legal challenge.
Such a challenge might emerge from human rights violations flowing
from the region, arising directly from a project for which either
funding or insurance had been provided.
BACKGROUND
AND REMIT OF MISSION
Within
the coming months, major international funders such as the World
Bank and the European Bank for Reconstruction and Development (EBRD)
will decide whether to provide up to $1.5 billion of public money
to finance a major new pipeline – known as the Baku-Tbilisi-Ceyhan
(BTC) pipeline - from the Caspian Sea to the Mediterranean. The
pipeline is intended to export oil to Western markets.
BP
is the lead company in the BTC Consortium (BTC Co.)
which intends to build the pipeline and is also the operator and
lead shareholder in the offshore oil fields in Azerbaijan which
would supply it. The route chosen is more expensive than many other
possible options for Caspian oil exports, and BP has said that the
pipeline cannot be built without "free public money".
The pipeline consortium is seeking public funds via the International
Finance Corporation (IFC) and the European Bank for Reconstruction
and Development (EBRD). At least six export credit agencies, including
the UK’s Export Credit Guarantee Department (ECGD), SACE (Italy)
and the US Ex-Im bank, have also been approached for support by
BTC. Formal applications for funding have been made to SACE and
Ex-Im but, as yet, none has been made by a UK exporter to the ECGD.
The project has not yet been accepted into the project pipelines
of IFC and EBRD. However, BP has signalled that it hopes to submit
an application at the end of April or beginning of May.
The
pipeline, which would be buried along its entire route, save surface
facilities, would transfer up to 50 million tonnes of crude oil
per annum (or one million barrels per day) from Sangachal on the
Caspian Sea coast, via Azerbaijan, Georgia and Turkey, to the Mediterranean.
Crude oil would be supplied to international markets via tankers
loaded at a new marine terminal.
In
Turkey, the BTC pipeline would stretch over 1000 kilometres, running
from the Georgian border in the north-east of the country to Yumurtalik,
south of Ceyhan, on the Mediterranean coast. An existing oil terminal
at Yumurtalik would also be expanded. Construction work is to be
carried out by BOTAŞ, the nationalised Turkish pipeline company,
under a $1.4 billion Lump-Sum Turnkey Agreement, whereby BOTAŞ
has agreed to construct the pipeline for an agreed price, thereby
relieving the BTC Consortium of the financial risks of any cost
overruns.
In
June 2002, over 60 regional and international Non-Governmental Organisations
(NGOs) wrote to the IFC, the EBRD and other financial institutions
raising a range of environmental, human rights, developmental and
environmental concerns. The groups urged that the IFC and other
potential funders "impose a number of conditions on loan approval
at the earliest possible stage of project appraisal" and that
no funding be provided "unless the project is able to clearly
demonstrate positive local and regional development impacts associated
with the project over the next 30 years."
Since
then, three international NGO Fact Finding Missions (FFMs) have
travelled the route of the proposed pipeline and revealed major
discrepancies between claims made by the BTC Consortium and the
realities on the ground. The discrepancies span a wide range
of issues, notably consultation and compensation arrangements, human
rights issues, and the projects’ benefits for the people of the
three host countries. Major violations of World Bank and EBRD standards
were identified – in Turkey alone, the project was found to break
four IFC safeguard policies on consultation and two on resettlement.
Concerns were also raised that the legal agreements signed between
the BTC and the governments of Turkey, Georgia and Azerbaijan are
in potential violation of the European Convention on Human Rights,
European Union laws and other international law instruments.
The
BTC Consortium has since made some improvements to rectify the deficiencies
identified by the FFMs and other NGOs, in particular on resettlement
and consultation. In November 2002, a Resettlement Action Plan was
made public, which was predicated on ensuring that all those whose
land would be affected by the pipeline will receive compensation
at a fair market price.
----------------------------------------------------------------------------------------------
BOX:
WHO BENEFITS FROM BTC?
BP and other
sponsors of the BTC pipeline argue that the BTC pipeline will bring
great benefits to the three host countries, in the form of government
revenues from transit fees.
The countries
would receive annual revenues from BTC as follows:
| |
2005-2009
|
2010-2020
|
from 2021
|
|
Azerbaijan
|
0
|
0
|
0
|
|
Georgia
|
$31m
|
$51m
|
$45m
|
|
Turkey
|
$51m
|
$110m
|
$97m
|
However, these
revenues sound less impressive when placed alongside some of the
potential and actual costs – especially in Turkey. The Turkish state
pipeline company BOTAŞ has signed a Turnkey Agreement with
the BTC partners, which commits BOTAŞ to building the Turkish
section of the pipeline for a fixed price of $1.4 billion. However,
analysts have commented that the real cost – even assuming no over-runs
– is more likely to be around $2 billion. Thus it seems likely that
the Turkish state has taken on a liability of at least $600 million,
in addition to any and all of the cost over-runs which almost inevitably
accompany any major pipeline project, which could bring its bill
into the billions. For comparison,
Even BP has
said that is thinks it is unlikely BOTAŞ will complete its
contract within budget and on schedule, and the Turnkey Agreement
states that in this eventuality the Turkish government will have
to pay a further penalty to the consortium, potentially of several
hundred million dollars. In all three countries, the governments
carry the costs of security, plus any legal liabilities for human
rights abuses caused by the security operation – costs which have
not yet been estimated. In Georgia, there is considerable risk to
the Borjomi mineral water facility, whose springs BTC would pass
close to, and which accounts for 10% of Georgia’s exports. Borjomi
is the largest mineral water brand in the former Soviet Union. While
Azerbaijan will gain revenue from the oil extracted from its territory,
it will get nothing from the pipeline itself. In other words, while
BP is therefore insulated against the many sources of financial
discomfort associated with pipeline projects, the likely costs of
BTC to the host countries, Turkey in particular, would seem to cancel
out many of the potential benefits.
In any case,
the development benefits of the BTC project itself are in serious
doubt. Firstly, extensive corruption in all three countries means
that benefits are very likely to be restricted to the elites. Secondly,
there are strong signs that Azerbaijan may be suffering from ‘Dutch
Disease’, the condition where an economy actually contracts due
to over-concentration on oil development at the expense of other
sectors of the economy. The IMF’s insistence that Azerbaijan set
up an Oil Fund specifically to combat this has been traduced by
the use of hundreds of millions of dollars from the Fund to pay
for the construction of BTC, a decision which led to the IMF suspending
further loans to Azerbaijan. Thirdly, given Baku’s history as the
oil refining capital of the former Soviet Union, the country would
arguably be better served by refining oil than by exporting crude.
Indeed, the refining sector has shrunk to a fraction of its former
capacity, causing a major skills exodus, and even requiring the
country to import petroleum products, with significant impact on
balance of payments.
----------------------------------------------------------------------------------------------
REMIT
OF THE FFM
On
16th-24th March 2003, a second Fact Finding
Mission (FFM) to Turkey, consisting of representatives from four
Non-Governmental Organisations, visited the region travelling along
the route from Sivas to Posof.
The
remit of the mission was to assess the compatibility of the BTC
project with World Bank/International Finance Corporation guidelines
on resettlement and consultation. This incorporated efforts to:
- Assess the
extent to which the prevailing human rights situation, especially
the level of freedom of speech, has impacted on the possibility
of legitimate consultation;
- Assess the
adequacy of the consultation process conducted as part of the
Environmental Impact Assessment (EIA) and the Resettlement Action
Plan (RAP) for the project;
- Assess the
proposed arrangements for compensating those affected by the BTC
project against the standards specified in the Host Government
Agreement for the Turkish section of the pipeline, namely the
Turkish Expropriation Law and the World Bank Group’s Operational
Directive OD 4.30 on Involuntary Resettlement;
- Assess the
extent to which affected communities have been informed about
the social and environmental impacts of the project and of their
legal rights with respect to damages and compensation, and chronicle
expressed concerns;
- Review the
impacts of the project on ethnic minorities, women and other vulnerable
groups living in the country and affected by the project;
- Learn the
views of politicians and relevant Parliamentary authorities as
to the implications for Turkey of the Host Government Agreement
(HGA) which Turkey has signed with the BTC Consortium and which
provides the legal framework for the project;
- Conduct preliminary
investigations into allegations made in the Turkish press of corruption
in the award of sub-contracts for work on the BTC pipeline.
Further
Fact Finding Missions are to take place later in the year, covering
the Azerbaijan and Georgian sections of the pipeline.
MEETINGS
CONDUCTED AND METHODOLOGY
The
FFM met with Parliamentarians, relevant Parliamentary bodies, affected
villages along the route, local leaders and individuals, political
parties, environmental and development NGOs, journalists, and experts
in engineering, environment, human rights and law.
Attempts
were made to meet with BOTAŞ in Ankara and subsequently in
Erzurum. Although the FFM made contact with BOTAŞ on three
separate occasions with requests (two verbal and one written) to
meet, the company failed to fulfil a tentative arrangement for a
meeting and refused to meet the FFM in the field. The FFM did, however,
meet Envy, the environmental engineering company which carried out
the environmental baseline survey for the EIA study under contract
to BOTAŞ.
The
FFM met representatives of seven villages, including four muhtars
(community leaders) and one deputy
muhtar, and spoke to one other muhtar on the phone. The villages
were chosen at random along the route. The FFM interviewed two of
the communities it had met in July 2002. Further visits to other
communities were planned but the FFM was prevented from carrying
them out due to police harassment and intimidation in Ardahan and
Kars provinces (see Section 1).
Of
these eight communities surveyed, three are in Sivas province, two
in Erzincan, one in Erzurum and two in Ardahan.
The
interviewing process was qualitative, beginning with open-ended
questions about people’s experiences of the project and the consultation
and compensation processes. They were thus able to raise concerns
and express opinions and feelings without being influenced by the
questions asked. The FFM followed this ‘open’ session with specific
questions about issues such as consultation and the compensation
procedures as a ‘spot check’ of BTC Co.'s claims in the EIA and
RAP.
All
five members of the FFM team took notes during meetings. These minutes
were typed and printed either the same day or the following day,
and checked by all members of the team. The minutes were an accurate
and full record of what was said.
For
reasons of protecting the security of interviewees from possible
harassment or other repercussions, the settlements visited and the
individuals interviewed are not named in this report. These names
are confidentially available from the authors. In most cases, interviewees
in urban centres were happy for their names to be given: where this
is the case, their names appear.
Section
1
BTC,
SECURITY AND HUMAN RIGHTS
A
great deal has been made by the BTC consortium of the extent and
sophistication of the consultation and compensation processes for
the BTC pipeline. The previous FFM to Turkey, carried out in July
2002, found that the consultation process was flawed both in design
and in practice. Since then, some improvements have been made, but
the flaws that have been addressed are primarily those arising from
poor implementation.
However,
what has not been dealt with — and in the FFM’s view cannot currently
be addressed, given the political context in which the project is
taking place — is the systemic inadequacy of the consultation
process in an environment where serious human rights abuses are
institutionalised. This is of serious concern: the reliance
of the BTC project on consultation goes much deeper than simply
eliciting information — it is the mechanism by which the BTC project
is supposed to be made a participative process, not merely one imposed
from above on people in the region. Consultation is thus integral
to the legitimacy of the entire project, before, during and after
its implementation.
1.0 THE
PREMISE OF CONSULTATION
By
BTC Co.’s own reckoning, during the period before construction,
consultation is the mechanism by which to "maximise [affected
people’s] understanding" of the implications and impacts of
the BTC project, in order that potential problems and grievances
are highlighted and resolved, and the project can gain local acceptance.
Indeed, the premise of creating regional "stakeholders",
on which BP / BTC Co have put much emphasis, depends entirely on
the existence of legitimate consultation.
Likewise,
during and after implementation, ongoing consultation, as part of
the process of monitoring, is the means by which inevitable mistakes
can be rectified and necessary improvements made. As the Resettlement
Action Plan (RAP) puts it,
"An
important part of the RAP is the establishment of a transparent
monitoring and evaluation process so that the RAP may be implemented
as planned and/or with appropriate modifications following the
timely and systematic input of affected groups. To further the
process of consultations with affected people that have already
begun, community feedback will be sought during implementation."
Moreover,
the monitoring framework of the RAP is structured such that "outcome"
and "impact" indicators, which reflect the damage done
by the pipeline and whether its benefits have percolated down to
local people, are predicated on "process" indicators,
which themselves depend almost entirely on effective consultation
and liaison with local communities. Examples of such process indicators
in the RAP include:
(i)
the creation of grievance mechanisms
(ii)
the establishment of stakeholder channels so they can participate
in RAP implementation
(iii)
information dissemination activities
(iv)
establishment of the BTC community investment programme.
Moreover,
many of the international financial institutions and other funding
bodies which are considering contributing to the BTC project have
put great store by the premise that consultation with affected people
will ensure the fairness and effectiveness of the pipeline for all
concerned. Therefore, effective consultation schemes are critical
to the BTC project gaining legitimacy not just at the local level,
but also internationally and with prospective funders.
1.1
HUMAN RIGHTS VIOLATIONS AND THE LEGITIMACY OF CONSULTATION
Effective
consultation is predicated on the existence of genuine freedom of
speech and of expression. If people cannot express their opinions
of the project, critical as well as supportive, reservations as
well as endorsements, in a free and open manner, consultation processes
cannot be valid.
In
assessing the extent to which such conditions pertain on the route
of the BTC project, the FFM cautions against the use of a narrowly-drawn,
legalistic view of "freedom of expression". As noted above,
consultation is key to the success or failure of the project, both
now and in the future. As such, it is important that consultation
is seen to be comprehensive and fair, both by groups involved
in the BTC project and particularly by locally affected people themselves.
On any view, at a minimum suggests:
- First, that
people are consulted in a genuine way prior to any decision being
formulated and that their views, adverse as well as accepting,
are taken into account;
- Second, that
people have the right and opportunity to express their opinions
freely and openly on a wide variety of topics related to the project,
not simply to respond to queries on a single subject;
- Third, that
people have the capacity to express dissent in the full knowledge
that no adverse consequences, direct or indirect, will result
from their doing so. Political culture is the key here: it is
disingenuous to expect that people used to framing their words
with the greatest of care will bring themselves to speak freely
to outsiders on any issue, let alone issues in which they perceive
the state to have an interest. Analysts of censorship are familiar
with the concept of "the chill effect", the tendency
of people living in repressive or constrained environments to
censor themselves rather than bring down trouble on their heads
by speaking out against authority. In such societies, much dissent
is never even voiced, let alone heard.
1.2 TURKEY’S
HUMAN RIGHTS RECORD
Given
the above, Turkey’s human rights record is of critical concern when
evaluating the prospects for a just outcome to the BTC project.
That the reservations over repression and dissent listed above clearly
apply to Turkey can be seen in its record at the European Court
of Human Rights (ECtHR). As of 10 February 2003, the ECtHR had ruled
against Turkey in 403 cases concerning torture, disappearance, extra-judicial
killing, the destruction and evacuation of villages, violations
of freedom of expression and other violations, with a further backlog
of 5, 236 cases pending.
With
regard to the BTC project, the violations to which Turkey has subjected
its Kurdish population are particularly relevant, since the Kurds
constitute one of the minority groups most impacted by the BTC pipeline.
The Turkish state’s doctrine of "indivisible integrity"
has meant that even insignificant Kurdish cultural expressions have
been treated as acts of "separatism" and thus repressed.
Much credit has been given to Turkey for its "Harmonisation
Law" reforms of August 2002, which were introduced to address
European Union concerns over human rights abuses, yet investigations
have shown that little or nothing has changed in practice. Prison
sentences are still being handed out to people for giving children
Kurdish names and for singing Kurdish songs at concerts. Likewise,
for Turks as well as Kurds, publishing critiques of Turkish state
policy leads - as a matter of course - to trials in military courts.
1.3 BTC
AND STATE REPRESSION IN THE NORTH-EAST
BP
acknowledges that Turkey’s human rights record is of concern, and
in particular that the record of the Gendarmerie, the military police
being used to provide security for the pipeline, is "not good".
Yet BP — and some IFIs — have taken considerable pains to assure
concerned parties that the situation along the pipeline does not
resemble that in the south-east, where human rights abuses have
been particularly prevalent due to the intensity of the recent 18-year
conflict between the former Kurdistan Workers’ Party (PKK), now
known as KADEK, and Turkish security forces.
The
FFM agrees: for much of the pipeline route, villagers – though reluctant
to criticise the state itself or what they considered to be a project
of the state – were in a position to speak to the FFM without overt
intimidation by state security personnel. From Kars to the Georgian
border, however, the FFM found conditions to be entirely different.
Here the Mission found clear-cut evidence of political repression
so systemic as to fundamentally invalidate the consultation exercises
that the project developers have undertaken. Indeed, the
FFM was itself detained by the Gendarmerie on two occasions and,
due to police harassment and intimidation, was forced to abandon
a number of planned visits to villages affected by the pipeline
for fear of exposing local villagers to potential human rights abuses
by the state security agencies.
In
the FFM’s view, repression in the north-east region of Turkey –
as manifested by arbitrary arrests and detentions, the inhibition
of dissent through police intimidation, and the constant surveillance
of critics by state security personnel – is such that implementation
of the project to international standards is currently unattainable.
Although the repression is largely directed at the local Kurdish
minority, which constitute approximately 30% of the population,
it is by no means restricted to the Kurds: the FFM
found an atmosphere of repression which weighs heavily on everybody
in the region, regardless of background or ethnicity.
Three
incidents, as detailed below, illustrate the extent and depth of
the problem.
- The Detention
of the FFM
On
the evening of 21st March, the FFM was confronted
- on two occasions - by the deputy chief of state security
in Ardahan and questioned about its itinerary and identity.
Subsequently,
the FFM was followed by undercover police and, en route to
a meeting in a local village, was stopped by the Gendarmerie.
The FFM, together with its translator and three local people
who were escorting the mission to the village, was then detained
in the Çamliçatak Gendarmerie station for over
an hour. Their passports and identity cards were retained,
and repeated requests for an explanation for their detention
went unanswered. Upon release, the FFM was followed for a
further half an hour, after which it was pulled over and obliged
to return to the Gendarmerie station for a second time.
On
this occasion, an explanation was proffered: namely, that
the FFM interpreter’s Turkish identity card needed to be verified
because her maiden name was not the same as her married name.
No explanation was forthcoming as to why this alleged problem
was not resolved during the previous detention. The FFM also
made contact with the UK and Italian embassies and the UK
Foreign Office, to whom several British parliamentarians made
formal expressions of concern. Contact was also made with
the Turkish government, which denied all knowledge. However,
the Gendarmerie refused to talk directly to an official from
the Italian Embassy in Ankara. (For a full account of the
detentions and harassment, see Box: Account of Detention of
BTC Fact Finding Mission by Security Services in Ardahan).
The
FFM was eventually released after a further half an hour.
On returning to its hotel, the FFM found that the luggage
of all bar one of the FFM members had been searched. It was
further suggested, though not directly by official sources,
that arrest was possible if the FFM did not stop interviewing
local groups. A formal complaint against the Gendarmerie has
been lodged with the British and Italian Foreign Ministries
by all members of the FFM.
Although
the FFM was treated with relative politeness (which does not
excuse the detentions and surveillance), the local people
detained along with the FFM made it clear that their own safety
was only assured by the FFM’s presence. When previously detained,
they had not been held upstairs in the waiting room of the
Gendarmerie station but downstairs in a freezing cell. As
one noted, "The taxes we pay don’t come back to us as
tea or food in Gendarmerie stations, but as truncheons. Believe
me, we are not exaggerating. You can only imagine 10% of what
happens here."
The
FFM notes that the detentions, harassment, intimidation and
constant surveillance which it experienced during its visit
are routine for many of those who live in the region. It would
therefore like to record its gratitude to those who were willing
to be interviewed, in spite of the risks that were clearly
involved. Indeed, given the repression that it witnessed,
the FFM deems it a significant measure of the extent of local
disquiet that so many interviewees were prepared to spend
time with the FFM detailing their concerns.
The
effect of the harassment experienced by the FFM was to render
its task of interviewing local villagers impossible, forcing
it to abort planned meetings with villagers anxious to discuss
their concerns over compensation. The constant and highly
visible tailing by several cars containing military and secret
police had the clear effect of intimidating not just the FFM
from conducting interviews but – perhaps more to the point
– local people from talking to the Mission. Yet, from the
interviews it was able to carry out, the FFM concludes that
such a crushing weight of control is entirely the norm in
the Kars and Ardahan regions. Indeed, the FFM has serious
concerns about the welfare of several of its interviewees
and will be monitoring their treatment over the next few months
as carefully as possible.
------------------------------------------------------------------------------------------------------------
BOX
Account
of Detention of BTC FFM by Security Services in Ardahan, 21-22/3/03
March
21, 17.00 hours. The Mission met a local journalist who
publishes an independent paper for the Ardahan region. As
part of his critique of lack of free expression in the area,
he noted that we were being followed by at least 4 cars. Earlier
we had seen plainclothes officers in the street, some of whom
had questioned our driver.
Suddenly
two men entered uninvited, with a further colleague waiting
in the street. They were wearing plainclothes and bore no
identification badges. Despite the journalist’s angry insistence
that they leave, the two men, without giving their names,
explained that they were security officials who had come to
"assist us" with any potential "security problems"
We made it clear that this was unnecessary, but were forced
to cut short our meeting due to the journalist’s increasing
distress at the men’s presence.
Outside
the office the men talked to us for a short period, asking
questions about our identity, which we willingly gave, and
itinerary, which we politely declined to answer. They did
not identify themselves.
18.00
We returned to our hotel, where the two men returned and questioned
us more intensively. Having discovered that one of the men
was the Deputy Chief of Security, we replied that they had
no right to investigate us; they denied that this was an investigation,
merely an offer of assistance and escort if necessary. We
responded that we had no need for their help, but that we
would be interested to hear details of the security threats
to which we were allegedly subject, since BP had informed
us on several occasions that the area presented no security
risk. We offered to pass on any information he gave us to
BP. He declined to provide details or, when requested, to
give his name. Eventually the Deputy Chief and his colleague
changed their requests, denying that they were interested
in our plans, and left.
19.00
The Mission was invited to visit the village of some local
people it had met in Ardahan that day. On our way to the village,
during which we were followed once again, we were stopped
by officers of the Gendarmerie at Çamilçatak.
After a few minutes of waiting, we were asked to enter the
Gendarmerie station, where our passports were retained and
we were held for approximately one hour from 19.45 to 20.45.
We were informed that we had not been officially detained,
and were provided with tea. However, the Gendarmerie refused
to answer repeated requests as to the reason for our delay
or its potential duration and we were not allowed to leave.
Because
of this, we made contact with both the Italian Embassy and,
via contacts in England, the British Embassy in Ankara and
the Foreign Office. Notably, the Gendarmerie refused to accept
several phone calls from the Italian Embassy seeking clarification
of the status of one of its citizens. Moreover, the soldiers
present also refused requests to put us in touch with more
senior officers.
Eventually
the FFM was released and its passports returned. No reason
was given as to why we had been held or released. After approximately
half an hour of driving, during which the ubiquitous tailing
took place once more, we were pulled over for a second time
and asked to return to the Gendarmerie station. On this occasion,
a reason for detention was eventually proffered: our interpreter’s
maiden name was different from her married name on her identification
cards. Why this issue was not resolved during the first holding
period was unclear.
During
the second period in the Gendarmerie station our passports
were taken once again. Additional personnel were present,
including a plainclothes officer who evidently understood
English but refused to talk to us. Again requests to see a
senior officer were denied, even when the Mission noted that
it would make a formal complaint about our treatment. By this
stage our contacts in England informed us that several parliamentarians
had made formal inquiries about our welfare. We were also
informed by the Italian Embassy that the Governor of Ardahan,
contacted as suggested by the Gendarmerie station personnel,
had declined to accept their call.
We
were once again released approximately half an hour later,
at 21.45, and were tailed on our return back to Ardahan. We
returned to the hotel to find that the luggage of all but
one of the members of the Mission had been searched while
locked in our rooms, and clumsily replaced. Nothing had apparently
been taken. We were also informed by a Turkish source who
is not named for security reasons that the colonel of the
local Gendarmerie was threatening to have us arrested if we
did not stop conversing with members of DEHAP, a legally constituted
political party which has taken up the Kurdish issue.
Alarmed
by these latest developments, the Mission made contact with
the British Consulate in Ankara. We informed him of our itinerary
for the next two days and promised to keep in touch. KHRP
Executive Director Kerim Yildiz also informed us that he had
made contact with the Turkish government, who had denied all
knowledge of our detention but suggested that we might have
been stopped for ID checks. While having dinner in the hotel’s
restaurant, we were watched constantly by State security operatives.
Later,
we heard that that evening the Gendarmerie had surrounded
several villages that had been celebrating Newroz, the Kurdish
New Year, blocking all entrance and egress. The Provincial
Governor had banned all such celebrations, although they take
place all across the Middle East and even in the South-East
of Turkey. Two men we had met were arrested that evening,
and one alleged that he was forced to pay a bribe of 440 million
Turkish lira (approx. £170, a huge sum in the region) to obtain
his release.
March
22. The following morning we were constantly surveyed
and followed, including as we had breakfast. We were unable
to carry out any meetings in villages, as we were followed
for the whole day. A well-placed source told us that BOTAŞ
had been responsible for our detention; rumours had been spread
that we were in the pay of a rival company to BOTAŞ,
seeking the contract for the pipeline.
We
stopped for lunch north of Ardahan in a small village. The
JITEM (secret service) tail pulled up behind us. As one of
our members went to buy cigarettes, a tailing security operative
burst into the shop behind her and screamed at the shopkeeper
not to talk to her.
When
driving from Ardahan to Kars we were again tailed – by two
cars and two Gendarmerie vans. In total, we calculated that
16 men had been assigned to follow us. Due to this heavy surveillance,
the FFM therefore cancelled a planned meeting with villagers
who had asked to see us in order that they could detail the
problems they were experiencing with compensation (see Section
3 for further details).
The
Mission later stopped en route for a female member of the
team to go to the lavatory. As soon as we stopped a Gendarmerie
van pulled over and four men got out of the van. In a rather
aggressive manner they asked what we were doing. Once we explained,
they got in the van and waited for us to resume our journey.
Later
on we were stopped outside Kars by members of the Gendarmerie
with our license plate number. They whistled us over and explained
that they had been ordered to stop the Mission, but unfortunately
the senior officer who gave the order had failed to tell his
subordinates what to do with us afterwards. They let us go
again.
In
the words of one of the local people who accompanied us that
night, "You give up in the end. You just get sick of
it and give up."
______________________________________________________________________
- The Banning
of Newroz
The
FFM visited the Kars and Ardahan areas over the period of the Kurdish
New Year festival, Newroz. The response of the state authorities
to attempts by local villagers to celebrate the festival provided
the FFM with compelling evidence of the state’s willingness to use
that power to suppress human rights.
Although
Newroz is widely celebrated across the Middle East, in past decades
the Turkish authorities took the view that the festival was being
used by the Kurdish population as a forum for Kurdish cultural expression.
Celebrations were therefore violently repressed, culminating in
the Newroz massacres of 1992 in which Turkish security forces killed
over a hundred celebrating Kurds. In recent years, the Turkish state,
realising that it was creating a focus of resistance, has reluctantly
embraced the festival, with the result that this year hundreds of
thousands of people celebrated Newroz peacefully in both Istanbul
and Diyarbakir, the largest city in the Kurdish regions of Turkey.
As
the FFM discovered, this liberalisation has not spread to the Kars
and Ardahan regions. In Ardahan province,
the Provincial Governor banned Newroz celebrations not just
in the towns but in the surrounding villages. The FFM learned that
Gendarmerie units had been sent to all local villages deemed likely
to engage in celebrations in order to ensure the ban was strictly
adhered to. The FFM was told of two villages that had been surrounded
by Gendarmerie in order to prevent anyone from entering or leaving.
Due to police harassment, however, the FFM was unable to verify
this independently.
The
FFM also learned of incidents of intimidation directed against the
local Kurdish population. One of the FFM’s interviewees told of
how he had used his car to bring tractor tyres back to his village,
in the corridor affected by the pipeline. He was detained by the
Gendarmerie and interrogated, on the premise that he was planning
to use the tyres to burn in Newroz fires, a central part of the
New Year celebration. His baffled response was to point out that
these were new tyres, intended for use on his tractor; if he had
intended to burn tyres, he would at least have bought second-hand
ones. Eventually, he was released. Others were not so lucky; one
interviewee told the FFM of how, having been arrested for celebrating
Newroz, he had to pay substantial bribes to get himself released.
The
FFM was also presented with evidence of other attempts to intimidate
people from celebrating Newroz. One interviewee showed the FFM a
letter he had received on the day of the festival, telling him he
had been given a large fine and a suspended sentence for allegedly
"endangering people’s lives with my actions" during Newroz
2001. He interpreted the timing of the letter as a flagrant attempt
to warn him off any action this year. The FFM is of the same opinion.
1.3.3 Increased
Detentions and Arrests
The
FFM interviewed members of DEHAP, the successor to HADEP, Turkey’s
main pro-Kurdish party. HADEP was dissolved on March 13 of this
year as part of what Kurdish groups claim is a process of systematic
disenfranchisement of their electoral interests.
The
chair of DEHAP’s Ardahan city branch noted that the last two years
had seen a relaxation of surveillance, following an easing of tensions
in the wake of the ceasefire declared by the Kurdistan Workers’
Party (PKK) in September 1999. However, both he and the regional
chair of DEHAP reported a marked rise over recent months in the
surveillance both of local people and of the party offices. The
regional chair also noted an escalation in the number of detentions
and arbitrary arrests. Both men cited the recent dissolution of
HADEP, DEHAP’s predecessor, as evidence that despite Turkey’s aspirations
to EU accession, fair and equal access to democratic rights was
still far from the norm.
Moreover,
in addition to citing specific incidents of repression, the DEHAP
representatives emphasised the psychological pressure to which villagers
in particular - Turkish as well as Kurdish - were subjected in the
region. Villagers were frequently stopped at checkpoints and asked
for ID cards, despite a lack of an obvious rationale or threat.
Both men suggested that this was part of the military and state’s
assertion of dominance in the region. This interpretation
accords with the FFM’s own experience. The FFM notes, for example,
that the security personnel who followed the Mission made no attempt
to conceal themselves, indicating that their presence was intended
to exert a "chill effect" that would inhibit the FFM from
action and local villagers from talking to the mission.
The
FFM was told that the resurgence in arrests and detentions in recent
months paralleled the increasing isolation by the Turkish authorities
of the jailed Kurdish leader Abdullah Ocalan, including denying
him access to his lawyer or other visitors. Many of those interviewed
by the FFM saw the two trends as connected and expressed fears of
a new clampdown in the region, on Kurds in particular. The FFM also
heard evidence that tensions in the Kurdish regions of Turkey have
been heightened by the invasion of Iraq and Turkey’s expressed desire
to move military forces into Iraqi Kurdistan. The FFM notes
that any increase in tensions – particularly if it results in a
breach of the Kurdish guerrillas’ ceasefire - would have grave implications
for both the security of the BTC pipeline and the human rights of
those who would live along it, should it be built.
Most
serious of all, the political context of the pipeline is influencing
people’s perception of the project, which in turn is compounding
resentment. The FFM heard the view expressed that there was a hidden
agenda behind BTC Co.’s systematically inadequate compensation levels.
"It is a deliberate policy designed to move people out,"
several respondents in one Kurdish village insisted. In the view
of these project-affected people, the combination of lost and damaged
land and inadequate compensation was intended to upset the delicate
calculus of their difficult rural lives, in order to further the
ongoing migration of people from ‘sensitive’ regions into mainstream
Turkish society which has been a documented focus of recent state
policy. This view concurs with those of political leaders
all over eastern Turkey, who often complain that their budgets are
systematically cut to further impoverish their regions. In the FFM’s
view, the fact that affected people are making these allegations
of a hidden agenda indicates a severe lack of local faith in the
legitimacy of both the consultation process for BTC and in the project
itself.
1.3.4
Denial of language rights
Consistent with
the other forms of cultural repression outlined above, through much
of the history of the Republic of Turkey, the Kurdish language has
been banned, in either written or spoken form. Indeed in 1924, the
year after the Republic was formed under the leadership of Mustafa
Kemal Atatürk, an official decree banned all Kurdish schools,
organisations and publications. Use of the words "Kurd"
and "Kurdistan" was forbidden and references to them were
removed from Turkish history books.
The Kurdish
language was banned outright until 1991, and even after that its
use remained highly restricted. With the Harmonisation Laws of August
2002, these restrictions began – in theory at least – to be lifted.
These laws allowed the teaching of Kurdish in schools, and the broadcasting
of programmes in Kurdish. However, their implementation in practice
is almost non-existent: to open a Kurdish language school requires
the permission of both the central government and the military-dominated
National Security Council in Ankara, while Kurdish TV is only allowed
to be broadcast two hours per week and must be subtitled or otherwise
translated into Turkish.
BTC Co has decided
not to publish the project documents in Kurdish, only Turkish and
English. The FFM believes that this decision is a tacit endorsement
of the historical linguistic disenfranchisement of the Kurds. With
the passing of the Harmonisation Laws, BTC Co, and BP – the operator
of the project, and a company which likes to claim to be more progressive
than its rivals – could have taken the opportunity to assert the
equal cultural and linguistic rights of the people living along
the pipeline route. It has declined to do so.
Furthermore,
in meetings held in Kurdish villages visited by the FFM, BTC / BOTAŞ
did not bring a Kurdish speaker, and held the meetings only in Turkish.
As a result, non-Turkish speakers in these villages, which include
the majority of women, were neither informed nor consulted at all
about the BTC project.
1.4
PIPELINE SECURITY AND THE GENDARMERIE
In
the light of the clear evidence of human rights abuses in the north-eastern
region, the security arrangements which have been agreed between
BTC Co. and the Turkish government are of deep concern.
Under
the legal frameworks for the BTC project, the responsibility for
security along the pipeline rests entirely with the Turkish government.
The Inter-Governmental Agreement (IGA) mandates that "each
State shall use the security forces of that State, and/or make provision
for such security personnel and services, as may be necessary to
satisfy this obligation, to ensure the safety and security of all
personnel…the Facilities, all other assets of Project Investors…and
all Petroleum in transit." This includes "the right of
access to and from its Territory" and "permit[ting] a
right of free movement in its Territory."
The
Host Government Agreement (HGA) goes further. Article 12 mandates
the protection of the pipeline and its personnel from the following
array of potential threats: "civil war, sabotage, vandalism,
blockade, revolution, riot, insurrection, civil disturbance, terrorism,
kidnapping, commercial extortion, organised crime or other destructive
events." No further clarification is given and no context provided
– which gives rise to concern that such vague rubrics provide significant
opportunities for misuse, and consequent
impacts on human rights.
Furthermore,
the responsibility for policing the pipeline has been placed in
the hands of the Gendarmerie. Whilst BP has pledged to use unarmed
local groups for immediate security along the pipeline route,
the company has still not at this late stage clarified exactly
what function the Gendarmerie will play – simply that they will
have "overall responsibility" for pipeline security. The
FFM notes with considerable alarm that the Gendarmerie is a military
police force implicated in many of
the very worst human rights abuses and atrocities perpetrated on
civilians in the Kurdish regions in recent decades. Indeed, its
record has been so poor that the Council of Europe has denounced
it on several occasions, the most recent being the Committee of
Ministers proclamation in July 2002, which recommended a total overhaul
of the corps.
Even
if Turkey were a country with a relatively unblemished human rights
record and a benign law enforcement agency, the FFM would be deeply
concerned that such an open-ended security rubric might invite human
rights abuses. Given Turkey’s human rights record and that of the
Gendarmerie, however, the FFM is firmly convinced that the security
arrangements envisaged for the pipeline, as mandated by the HGA,
make it a high risk that human rights violations will occur.
The
FFM notes that the HGA includes no clauses aimed at preventing what
the BTC Co refers to as "overly zealous" behaviour on
the part of the security forces. On the contrary, the FFM notes
that BTC Co / BP has attempted to put as much distance between itself
and the whole security issue as it possibly can. As BP representatives
told members of the FFM at a January 2003 meeting, "Security
is an obligation of the state; a sovereign state must ensure
the safety of its people and territory. The HGA is completely consistent
with that." Consistent with that position, the HGA not only
places all the responsibilities and costs for security onto Turkey;
it also insulates BTC Co from the cost of potential court cases
for human rights violations in the course of protecting the pipeline:
"As
among the Parties, the Government shall be solely liable for
the conduct of all operations of the security forces of the
State and neither the MEP Participants nor any other Project
Participants shall have any liability or obligation to any Person
for any acts or activities of the security forces of the State
or be obligated to reimburse the Government for the cost and
expense of providing security as contemplated hereby."
In
addition, the Host Government Agreement requires the state to compensate
BTC Co if it fails to fully protect its security. With the Turkish
state liable to lose money if there is a civil disturbance of any
sort, the FFM believes that this financial incentive – coupled with
the Gendarmerie’s current approach to enforcing security - is very
likely to lead to "over-zealous" policing.
The
FFM is also concerned that the HGA contains no effective mechanisms
for ensuring state respect for local people’s human rights.
BP has talked of introducing a set of "Voluntary Principles
on Security and Human Rights" as a protocol to the HGA. As
yet, however, no text has been made public. The voluntary status
of the proposed principles, combined with their late arrival and
conspicuous absence from the original agreements which so carefully
ensure the rights of the project participants, gives the FFM no
confidence as to the mitigatory powers of such a protocol.
Finally,
the FFM notes that none of the villagers to whom the FFM spoke were
aware that by signing deals with BTC Co., they have given license
to the military police to come onto their land. Not a single person
who the FFM interviewed was aware that any arrangements had been
made for securing the pipeline, let alone that they involved the
Gendarmerie. Inquiries as to whether people had been told there
might be security issues surrounding the BTC project were met with
blank looks. The FFM was left with the strong impression that BTC
/ BOTAŞ, in violation of their responsibilities, had entirely
failed to warn people of the possible negative outcomes or implications
of the pipeline. Communities along the pipeline route may thus
have signed away their land without the slightest indication that
this might involve visits or surveillance from the military.
1.5 BTC
AND FREEDOM OF EXPRESSION
The
FFM’s findings directly challenge two key claims surrounding the
BTC project: firstly, that the pipeline does not pass through any
areas in which security and human rights violations are an issue;
and, secondly, that the BTC pipeline will not worsen or exacerbate
the human rights situation along the route.
From
the evidence of repression it received from interviewees, and the
corroborating evidence it experienced first hand, the FFM concludes:
- The
lack of freedom of expression in the Kars and Ardahan regions
renders wholly illegitimate the consultation processes that the
BTC Co. has carried out. The FFM considers it untenable
to suggest that people subject to the kind of duress that it witnessed
would be in a position openly to object to a project of great
importance to the state, being carried out by the state pipeline
company.
- The
flawed and inadmissible consultation processes carried out by
BTC Co. have in themselves compounded the atmosphere of human
rights repression in the north-east, by giving a veneer
of collective participation to what is in reality a state-imposed
decision on local people. In failing to take proper
account of the repression in the region, BTC Co. have arguably
further disempowered rather than empowered local people, by extracting
their sanction for a potentially damaging project when they had
no option but to give it. This has reinforced the position of
the state and further contributes to the very atmosphere of human
rights repression in the region, which BTC Co. has denied exists.
- The
prospect of a legitimate consultation process being carried out
in the absence of major human rights reforms is unattainable.
The problems relating to repression are so systemic as to transcend
particular social groups: in the FFM’s view, they are the product
of a state and military which is intolerant of dissent and freedom
of expression. There can be no such thing as genuine consultation
when those ‘consulted’ enjoy neither the right nor the conditions
in which to say what they think.
- The combination
of the desire of the BTC consortium to insulate itself from the
security issue, the investment of security powers in a military
body with an internationally-criticised human rights record and
the atmosphere of repression and intense surveillance which characterises
large stretches of the pipeline route, make a marked increase
in human rights abuses and violations - both immediately and in
the long-term – highly probable.
Since
these factors are chronic, systemic aspects of the political situation
in Turkey, and thus cannot be readily fixed nor glossed over, the
FFM sees no alternative but to call for a moratorium on the BTC
pipeline project until independent monitoring deems them to have
been addressed.
Section
2
CONSULTATION
AND DISCLOSURE OF BTC PROJECT INFORMATION
Consultation
and disclosure of information are critical for the effective participation
of those people who are impacted by the project. Those affected
and other interested parties are entitled to be consulted so that
they are in a position to influence the project’s outcome, positively
or negatively.
In
March 2003, the FFM sought to assess; first, the extent to
which a legitimate consultation (which implies the existence of
freedom of speech) is possible in Turkey; and, second, the
adequacy of the consultation process conducted as part of the Environmental
Impact Assessment and Resettlement Action Plan.
Section
1 set out the FFM’s findings with regard to freedom of expression
and the political culture pertaining in Turkey. In this section,
the FFM’s findings on the consultation process itself are presented.
On paper it would appear that consultation has been conducted in
a way that addresses the interests and needs of the project affected
people. The FFM, however, concludes that the consultation to date
does not fully comply with international and domestic requirements.
2.0
SUMMARY OF PREVIOUS FACT FINDING MISSION FINDINGS
In
the last Fact Finding Mission in August 2002, the Mission found
numerous inadequacies and failures in both the design and the implementation
of the consultation procedures. The FFM found that the project violated
four of the World Bank’s safeguard policies on consultation. The
FFM also found that the project failed to satisfy the guidelines
contained in the International Finance Corporation’s (IFC) manual
Doing Better Business Through Effective Public Consultation and
Disclosure, according to which a project sponsor is to ensure
that the process of public consultation is accessible to all potentially
affected parties, from national to local level.
In
particular, the Mission found:
- Half of the
affected communities listed as having been consulted were, in
fact, not consulted.
- Where villages
had been consulted, the consultation could not be deemed meaningful.
- The consultation
package failed to take account of the political culture in Turkey,
which prevented the free expression of critical views about a
State-backed project.
- The inadequate
design of written information disseminated by BTC/BOTAŞ was
insufficient to secure an informed response. The wording of the
questionnaires discouraged frank expression of concerns about
the pipeline’s impact.
- The consultation
package failed to acknowledge the status and concerns of Turkey’s
minority groups.
2.
1 FRAMEWORK OF CONSULTATION
2.1.1 Environmental
Impact Assessment (EIA)
The
Environmental Impact Assessment (EIA) consultation process is subject
to international and domestic requirements on consultation. According
to BTC Co.’s Public Consultation and Disclosure Plan (PCDP) the
consultation process will conform to Turkish regulations as well
as guidelines established by international organisations, specifically,
the requirements of the International Financial Corporation of the
World Bank Group, European Bank for Reconstruction and Development
(EBRD), European Commission and other relevant international conventions.
In
addition, the PCDP aims to:
- "Identify
key stakeholders and ensure there are adequate mechanisms for
stakeholder feedback and information sharing."
- "Provide
an outline for consultation at the local, national and international
levels, starting at the project planning stage, and continuing
throughout the construction, operation and decommissioning of
the pipeline."
- "Ensure
issues raised by stakeholders are addressed in the EIA report
as well as in project decision-making and design phase."
- "Outline
a grievance mechanism for local stakeholders."
In
particular, the BTC project in Turkey is governed by the Host Government
Agreement (‘HGA’), which overrides all national laws except the
Constitution. The consultation process takes place in accordance
with Appendix 5 of the HGA, which requires that the EIA be released
to the public for review and comment in accordance with the following
procedures:
- Key stakeholders
shall be notified of the nature of the project during the development
of the EIA.
- Upon completion
of the EIA, the public shall be provided with information on
the environmental aspects of the project to enable it to comment.
- A maximum
of 60 days shall be allowed for public comments.
- Once approved
by the Government, BP, BTC Co and BOTAŞ shall implement
mitigation and monitoring activities.
International
standards, including the World Bank Group’s Environmental Assessment
Policy OP 4.01, January 1999 and the IFC’s manual Doing better
business through effective public consultation and disclosure: a
good practice manual, emphasise that all potentially affected
parties at national and local level be consulted. In particular,
the sponsor has to ensure that:
- Project
information is meaningful and easily accessible;
- all
stakeholders have early access to project information;
- the information
provided can be understood;
- the locations
for consultation are accessible to all who want to attend; and
- measures
are put in place which ensure that vulnerable or minority groups
are consulted.
In
addition, both the IFC and the ERBD require a thorough scoping procedure
for all Category "A" projects (of which the BTC pipeline
is one), which, in this instance, would involve BTC/BOTAŞ consulting
all relevant stakeholders during scoping and before the terms of
reference of the EIA are finalised.
The
FFM found that BTC Co. has failed to adequately comply with the
majority of the aforementioned standards. In particular, the FFM
found that:
- Not all
stakeholders had early access to project information.
- Not all
stakeholders were notified of the nature of the project during
the development of the EIA.
- There was
a consistent lack of provision of information about the project’s
negative impacts and risks, while the potential benefits of
the project were consistently overstated.
- Due to
the absence of early consultation, stakeholders were deprived
of a meaningful opportunity to raise their concerns at a stage
when these could have influenced the EIA process.
- On completion
of the EIA, a significant section of project-affected people
were not provided with information on all the environmental
aspects of the project to enable it to comment.
- The project
information provided could not be understood by a relevant number
of villagers affected and consultation was not accessible to
all those who wanted to attend.
- No assessment
was carried out as to the extent to which meaningful consultation
was possible, in particular with regard to the consultation
of those belonging to vulnerable and minority groups.
- In some
instances, grievance mechanisms for local stakeholders have
not been outlined.
2.1.2 Resettlement
Action Plan (RAP)
In
recognition of the World Bank/IFC policies on consultation and participation,
the BTC Consortium has produced a Resettlement Action Plan (RAP).
Consultation, participation and the establishment of a process to
redress the grievances of affected people are seen as a key step
to achieve the goals mandated by the World Bank and the IFC.
Specifically,
the RAP commits itself to:
- "establish[ing]
a process of consultation with the affected populations, and with
local public and civic organisations [to] maximise understanding
[…] implementation arrangements for resettlement, expropriation
and compensation;"
- "provid[ing]
straightforward avenues for people to lodge a complaint about
the project and obtain redress;"
- "inform[ing]
all directly affected communities in advance so that tenants can
make clear cut compensation sharing agreements with owners when
drawing up future leases;"
- "ensur[ing]
that the RAP is publicly available throughout the Project area."
- COMPLIANCE
WITH INTERNATIONAL STANDARDS ON CONSULTATION
2.2.1
Inadequate Consultation on the EIA and RAP
The
FFM visited a number of concerned organisations that had been identified
by BTC/BOTAŞ as having been consulted. The FFM found serious
flaws in the process of consultation of these groups that, according
the standards set out in Section 2.1 above, should have taken place
during the scoping period and, in any event, at an early stage of
the process. This group included two NGOs, three journalists, representatives
of one political party in different localities, the Chairman of
the parliamentary Human Rights Commission and the Chamber of Agriculture
of an affected district. The FFM found that of all these concerned
parties few had been informed about the project and those which
had been consulted were not satisfied with the consultation process
as a whole. Specifically, the FFM found that:
- The Worldwide
Fund for Nature (WWF) - a key stakeholder of the voluntary sector
- had not been notified of the nature of the project during the
development of the EIA. As one of the oldest nature conservation
organisations in Turkey, WWF had expected to be one of the first
organisations to be approached by the consortium. The FFM learned
from the WWF that they had not been informed about the project
until after the draft EIA had already been published. Their first
contact with pipeline companies was at a public meeting. WWF felt
that, at that late stage of the process, it was not possible for
them to influence the project in any meaningful way, nor indeed
to assist in the preparation of the EIA. In a letter, dated 20.9.02,
WWF raised their concerns regarding the participation process
but BTC’s response merely referred them to the PCDP for a detailed
account of stakeholder consultation throughout the EIA process.
Despite WWF’s concerns that they had not been consulted at an
earlier stage, BTC Co. has decided to include them in the stakeholder
list of the EIA to which WWF was referred in the first place.
- The Chamber
of Environmental Engineers, a highly respected professional body,
was not consulted. The FFM was not able to determine whether other
semi-official bodies that the FFM would have expected to
have been consulted had indeed been consulted. The Chamber of
Engineers was extremely concerned and dissatisfied with the consultation
stage of the project. They said that they had received information
only shortly before a public meeting on the BTC project took place
and that, in any event, the EIA had already been drafted. A further
concern expressed was that the meeting had been unofficial and
no transcript of the meetings would be readily available. It was
only after the meeting that the BTC Consortium directly contacted
the Chamber via email and asked them to comment on the EIA. Given
the time constraints and the length of the EIA, the Chamber was
only able to send a bullet point list of concerns and objections
to the EIA and the consultation process. When the FFM met with
the Chamber they were still awaiting a response from the BTC Consortium.
The FFM finds that, although the EIA’s Public Consultation and
Disclosure Plan (PCDP) states that the Chamber of Environmental
Engineers was consulted at a public meeting in Ankara, the Chamber
did not consider that the public meeting amounted to meaningful
consultation. According to the CEE representatives whom the FFM
met: "the whole process of consultation was all a facade".
- The Chamber
of Environmental Engineers told the FFM that, in the past, the
EIA of major engineering projects would be submitted to the Ministry
of Environment for review and approval. In the case of the BTC
project, this procedure had been bypassed and the Ministry of
Environment was invited as a guest at the public presentation
meetings, not as a host. This, the Chamber said, was contrary
to the procedure followed in other major Turkish engineering projects.
As a direct result of this procedure, the Chamber thought that
the EIA process was not officially binding; in other words, were
the Ministry to have any objections to the pipeline process, the
BTC Consortium would have no obligation to take account of them
or to make suggested changes. In the words of Chamber President
Ethem Torunoğlu,
"We
would like to emphasise the differences between a normal EIA
and this one. In the past, even though there were political
interventions for other projects, a proper public consultation
on EIAs took place and there was an interaction. With this project,
things have been totally different. Before, CEE was invited
to attend consultation meetings and then to make submissions.
After the consultation process it would generally take the EIA
consultants a year to make changes according to our objections."
In
this case, however, the FFM finds that, due to late consultation,
BTC Co. would not have been able to incorporate the Chamber’s
comments to the process and thus the consultation was useless;
the EIA was already drafted by the time it came under the engineers’
scrutiny. The Chamber expressed extreme concern that this effectively
amounted to the wholesale privatisation of processes that have
to include representatives of civil society. "This sets a
terrible precedent: what is the use of professional environmental
engineers or civil society? Everything can be done by private
companies."
- In Kars and
Ardahan, DEHAP, a national party which in these provinces
was the largest single vote-winner in the last elections,
with 23,467 votes and 9,700 votes respectively, was not provided
with any information about the project. DEHAP local representatives
told the FFM that they had not received any written documentation
relating to the project. Of even greater concern is the fact that
DEHAP was not even invited to attend any of the public meetings
held in the area. This is of particular concern given the security
situation and the lack of freedom of expression in the north-east.
In these circumstances, a political party, widely supported in
the area, can become the only channel through which project affected
people might be able to voice their objections and concerns.
- The Chairman
of a Chamber of Agriculture of a district affected by the pipeline
told the FFM that, although the Chamber keeps records of and has
direct dealings with most of the landowners in the area, he was
only consulted once, four years ago. In the Chamber’s district
there are eleven villages directly affected by the BTC project.
Though he had been given some leaflets and other larger documents
on the BTC project, he was not satisfied with the fact the Chamber
had only been consulted once.
- A previous
mission, carried out in July 2002, had questioned BTC Co.’s /
BOTAŞ’ assertion in the EIA that the muhtar (community leader)
of Hacibayram had been consulted by telephone, pointing
out that the village of Hacibayram is deserted and has neither
people living there nor telephones (see Box: Hacibayram-The
Continuing Mystery). The FFM attempted to visit the muhtar of
Hacibayram, but he was out of town at the time of our visit. The
FFM was keen to speak with the muhtar, because of the recent insinuations
that the previous mission had exaggerated or concocted its account
of the failures to consult in Hacibayram. Several follow-up phone
calls to the muhtar, Abdurrahman Aksu, after the FFM returned
home, established the inaccuracy of this suggestion. Mr. Aksu
stated that his first contact with BTC/BOTAŞ was only to
correct their misconception that Hacibayram was still inhabited,
but that he had not been meaningfully consulted prior to the publication
of the EIA. He was insistent that there was still no settlement
in the village, and that farmers merely went there in the summer
to farm. Far from being "aghast" at the FFM suggestion
that Hacibayram is an empty village, as the IFC suggested to FFM
members he was, he observed, "Why should we feel sad about
it? It is the truth."
- More importantly,
Mr. Aksu noted the inadequacy of consultation and especially of
compensation in the village. He said he had been visited by BOTAŞ
personnel, from Erzincan, only once during the whole consultation
and compensation process, shortly before the FFM´s recent visit.
He had subsequently been to Erzincan for further information but
was unable to get access to BOTAŞ staff. Worst of all, far
from consultation being comprehensive and compensation generous,
as the FFM was told by both BP and the IFC, the village is very
unhappy. One prominent family, he reported, has sued BOTAŞ
for their refusal to distinguish between irrigated and non-irrigated
land when apprising compensation values. Because of the village’s
failure to accord with BTC/BOTAŞ price for land, alleges
the muhtar, BTC/BOTAŞ has suspended all payments to the village
while the court case and disagreements continue.
- Dr. Coşkun
Yurteri, Deputy Chair of ENVY, the environmental engineering company
which was a secondary subcontractor for the basic engineering
phase of the EIA and one of the two primary subcontractors for
the detailed phase, recognised that the HGA requirements as to
consultation and the time frame for the consultation period were
so stringent that the company had to contact the Ministry of Environment
unofficially a year before the project started. Normally, said
Dr. Yurteri, there would be 60 working days
for the Ministry of the Environment and Natural Resources to review
and approve the EIA; "this time everything had to finish
within 30 days—it was all squeezed down," he noted. Because
of this, he said, an unofficial liaison with the Ministry of Environment
was established just in case someone came up with a difficult
question that they would have to answer later on. He was unable
to provide more details and it was unclear which departments were
consulted and to what extent during the scoping phase of the EIA
process. This irregularity reflects, in the view of the FFM, an
awareness that the consultation of key stakeholders and governmental
bodies was inadequate and that ‘alternative’ mitigation measures
had to be found.
--------------------------
BOX:
Hacibayram – the continuing mystery…
The previous
FFM to Turkey, undertaken in July 2002, visited one village, Hacibayram,
which was marked in the EIA as consulted by telephone, but which
was now empty, the residents having left during the recent conflict
between Kurdish guerrillas and Turkish state security forces. Since
that FFM’s reports, a number of explanations have been given, by
BP, by ERM (the contractor which carried out the EIA consultation)
and by the IFC. However, these explanations contradict each other,
both on the issue of how and why the villagers left, and on how
they were in fact consulted. Indeed, BP has given different accounts
on two different occasions.
The second FFM
was unable to travel to the village due to snow, and could not meet
the Muhtar (who now lives in Tercan), because he was away. However,
it did speak to the Muhtar three times on the phone. He also contradicted
several of the accounts, especially that of the IFC. In particular,
these calls indicated that the first FFM was correct that Hacibayram
was not properly consulted, in contradiction to what was stated
in the EIA, and that the Muhtar remained unhappy with the village's
treatment by BTC/BOTAŞ
The claims and
counter claims are listed chronologically below:
"Hacibayram
village in Erzincan province, marked on Map 20 C of the EIA's Supplement
II Series C: Social Baseline Maps as having been consulted by telephone,
had been deserted for many years, its houses having fallen into
ruins. There were neither telephones nor anyone to answer them.
Some former residents still come to the village area, but from the
FFM's interviews, it was clear that none of them had been consulted.
There had been rumours of plans for the pipeline, but never from
official sources."
- International
Fact-Finding Mission (CRBM, KHRP, Corner House, Ilisu Dam Campaign,
PLATFORM), BTC – Turkey Section, Preliminary Report, August 2002
"Their point
really is not the whole story", says Halton. "The villagers
- a community of some eighty people - left during the 1990s because
of the violence of the Kurdish Workers’ Party (PKK). It’s a sad
fact that they had to abandon their houses. They still regard themselves
as a community. We are in touch with those people and will see that
they receive compensation".
- Barry Halton,
BP’s Regional Affairs Director for BTC, interview on OpenDemocracy.net,
Globolog, 3/12/02, ‘The Baku-Ceyhan oil pipeline - BP replies’
"The people
have left the village, but some of them still come back to graze
their animals etc. We consulted with those villagers when they returned."
- ERM, speaking
to protesters at demonstration at ERM Manchester office, 13/1/03
The villagers
have been moving away to Tercan, a town 19km away, since the 1950s,
to get better schools jobs and facilities. The last five families
left in 1994. There was unrest from 1989 to 1995, but the village
itself was not affected; in Alsalce village, 20-30 km away, people
were killed, in Rezabe, Goçdeye and Yamanla most people moved
away because of unrest.
Nobody has given
up their land rights; there are 29 Turkish Sunni households and
one Alevi (who rented). Some families go back in the summer to farm,
some rent out the land. They still see themselves as Hacibayram
villagers; the Muhtar is still registered and gets a stipend, still
deals with administrative matters. They were "aghast"
to be thought of as an "abandoned village", and the other
nearby villages feel the same.
The BTC contact
was made through a phone call to a member of the Elders’ Committee,
whose son took the call and gave them the information, but never
mentioned the community no longer lives in Hacibayram. They have
all now had individual meetings, and all bar one have signed agreements.
They are very happy with the consultation process, and are being
treated like human beings. They want to go back to the village and
have applied to the government’s Return to the Village programme.
They have even suggested to BTC that they site a construction camp
in the village.
What concerns
us is that people are saying this was some kind of set-up. It happened
before the summit in Johannesburg, and there was all this furore
about the "abandoned village". The Muhtar still gets a
salary, and the people still consider themselves a community. This
wasn’t researched well. The guy who goes back most to the village
said he met some foreigners who didn’t say who they were, just that
they were doing an investigation.
- Ted Pollett
(IFC), meeting with KHRP, 26/2/03. From contemporary notes taken
by KHRP
"The people
left because they were economic migrants; they went to a nearby
town but still cultivate the land."
- BP presentation
to NGOs and SRI investors, 24/3/03
There is still
no settlement in the village. The farmers as usual go there during
summer to perform some farming, and that is all. A Top family has
sued BOTAŞ, the accusation being no distinction had been made
between irrigated and non irrigated land. Since the case is going
on this family has not been paid any compensation yet. I don’t know
the
details. I send my greetings to you all.
- Abdurrahman
Aksu, Muhtar of Hacibayram, phone conversation with FFM, 30/3/03
I’ve been visited
by BOTAŞ only once during the whole process, and that was about
a month ago. These were BOTAŞ people from Erzincan. I once
went to Erzincan to meet them, but was not able to see BOTAŞ
people then. I called Ankara BOTAŞ earlier today to ask about
the money to be paid to my fellow villagers (I haven’t got any land
to be expropriated, therefore my efforts are for my fellow villagers,
but not for myself). The result: BOTAŞ says the payment has
been suspended due to disagreements about the
prices.
[Asked about
the village being empty, and their feeling about FFM articulating
this fact in its report]: "Why should we feel sad about it? It is
the truth."
- Abdurrahman
Aksu, Muhtar of Hacibayram, phone conversation with FFM, 2/4/03
[When specifically
asked if he was contacted by telephone or otherwise before summer
2002, i.e. before the EIA was published]:
Some people on behalf of BOTAŞ visited TERCAN before the EIA.
I myself was not there. And some other person from Hacibayram misled
those visitors telling them that there was still settlement in the
village at that time. However, soon after this incident some lady
whose second name was Caglayan called me. On this call, I made a
correction on the other villager's declaration about the village
being inhabited. Meanwhile, I would like your assistance about the
payments to be made. Some of my fellow villagers called BOTAŞ
very recently about the payments. Even though some of the villagers
have been paid, some haven’t yet, and that this makes people uneasy.
- Abdurrahman Aksu, Muhtar of Hacibayram, phone conversation
with FFM, 8/4/03
---------------------------
2.2.2
Inadequate Consultation of Directly Affected People
The
Mission visited seven rural communities along the pipeline route
from Sivas to Posof, interviewing four muhtars and one deputy muhtar.
All of the rural communities were within the four-kilometre-wide
pipeline corridor and all are listed in the BTC EIA as having been
consulted about the pipeline either in person or by telephone. The
FFM found, however, that the standard of the consultation was low
and fundamentally flawed in several respects.
- Villagers
told the FFM that they were not provided with information on the
negative environmental impacts of the project. One villager
told the FFM that at the consultation meeting in the village they
had been informed that, as a result of the project, their land
would gain value and that there were no environmental risks. Some
villagers told the FFM that they were unaware of a decommissioning
stage. When the FFM explained some of the environmental risks
involved, one villager summed up his surprise at this new information
as follows: "Had I known that before, I would not have let
BOTAŞ build on my land. I would not have signed the documents
unless BOTAŞ committed itself to decommissioning."
- The same
villagers interviewed by the FFM were told that compensation would
be generous, contrary to the findings of section 3 of this report.
The villager, quoted above, was subsequently sent a letter from
the bank informing him that compensation had been paid at a fixed
rate, which he described as below market value. Thus, not only
was the procedure followed irregular, but also the amount offered
was significantly less than the villagers had expected after the
consultation meetings. This led to much disappointment and in
some cases the withdrawal of consent to the project, to the extent
that villagers vowed not to give BOTAS their land (although by
this point many of them had already signed legal forms).
- Representatives
of all villages visited by the FFM expressed concerns about the
way the information had been provided. They said that the
information was too technical and that the lecture-format meetings
were not helpful; too much was said and shorter, more frequent
meetings would have been better. Even those who had
received written information said that it would be of no
use to most of them, as many villagers could not read. Once again,
this illustrates that what on paper may seem adequate consultation
is sometimes in practice inadequate.
- All of
the villages visited said the documentation provided was too technical
and lacked clarity. The villagers still had unanswered questions
regarding their rights to negotiate a fair price for land, the
length of the construction period, the likely damage accruing
from the building works and the future use of the land affected
by the corridor.
- The FFM gathered
that the information given regarding the means of redress in case
of complaints was confusing and one-sided. In some instances,
the villagers were simply not told anything about their legal
rights. In others, they were openly discouraged from seeking redress
from the courts as, according to the consortium, it would take
a long time and they would in any event fail to obtain a better
price for their land. And, finally, some were told that to go
to court was not an option and that the expropriating agency would
not be bearing the legal costs. This failure goes to the core
of the process and breaches the project’s own guidelines.
In
a further illustration of the opacity of the consultation process,
the FFM was denied the chance on two consecutive days to obtain
an appointment with local BOTAŞ officials. The FFM was later
informed by the Social Team Coordinator in the Community Investment
Programme of the BTC Directorate in Ankara that BOTAŞ field
staff would not be able to meet with the FFM. The reason for this,
she said, was that BOTAŞ was part of the Turkish state and
thus subject to rules that stipulate that public officials cannot
meet journalists or NGOs without official approval. However, she
went on to say that the FFM would be welcome to meet them in Ankara.
The FFM is seriously concerned that villagers’ associations, either
seeking to gather further information or to raise the concerns of
those they represent, will be refused local meetings and invited
to travel to Ankara to obtain an answer to their questions. This
would be in direct breach of the relevant standards applicable to
the consultation process.
In
several of the villages the FFM visited and in meetings with other
interested parties, the FFM was plied with the very same questions
– for example, how was it decided how much people would be
paid for their land? Why was it less than what others were supposedly
receiving elsewhere? What would be the impact of construction on
their land? – that the RAP was designed
to address. This amounts to further evidence of the inadequacy of
the consultation process.
2.3 FLAWED CONSULTATION
DUE TO LACK OF FREEDOM OF EXPRESSION
Consultation
requires freedom of expression. In order for any consultation process
to be legitimate, it must firstly assess the extent to which those
consulted are able to freely express their opinion without fear
of repercussion. However, the FFM has not been able to discover
any evidence to indicate that such an assessment has taken place;
no reference to this is made in the EIA or the RAP. Had such an
assessment been undertaken, it would have become clear that the
conditions do not currently exist which would enable meaningful
consultation to take place, at least in the north-east of the country.
Furthermore, in the FFM’s view, this assessment becomes of crucial
importance when consultation is to take place in a country with
a well-documented poor human rights record. The European Court of
Human Rights has found Turkey in breach of the right to freedom
of expression in numerous cases.
The
IFC’s Consultation and Disclosure manual emphasises the need for
the project sponsor to ensure that the process of public consultation
is accessible to all potentially affected parties and that measures
are put in place, which ensure that vulnerable or minority groups
are consulted.
In
addition, it is recognised that consultation is a key step when
undertaking these types of projects. The Resettlement Action Plan
(‘RAP’) states:
"A
key step in the World Bank/IFC policies on resettlement, land acquisition
and
compensation is a framework for public consultation, participation
and
the
establishment of a process to redress the grievances of affected
people.
Consultation
with the affected population and with officials of local
government,
civil society and other representatives of the affected population
is
essential for gaining a comprehensive understanding of the types
and
degrees
of adverse effects."
As
recognised by the IFC, " in certain countries and contexts,
public consultation with local communities can be politically sensitive
and therefore actively discouraged or limited by local and national
government." Further, the IFC states that "political factors
should not be considered insurmountable obstacles, however, nor
should they be seen as excuses for failing to consult with locally
affected people."
Whilst
recognising the complexity of this task where the process encompasses
a vast geographical area, the FFM finds that the sponsors of the
project failed to put measures in place to assess whether project
affected people in the north-eastern region were obviously constrained
when expressing their views. The systemic and the specific failures
to acknowledge the security situation along sections of the pipeline
are dealt with elsewhere in this report. Both the EIA and the RAP
are silent on potential limitations on the freedom of expression.
On the contrary, far from measures being taken by the project developers
to ensure affected people did not feel intimidated during meetings
with officials, the BTC Consortium clearly permitted members of
the feared Gendarmerie to be present. As the RAP recalls:
"BOX
7.1: Kelkit/Gumushane, August 2001: Participants of the BTC
information
meeting included the district governor, district Director of
Agriculture,
Commander of Gendarme, district security director, Mayor
and
12
villages headmen" (FFM emphasis)
"BOX
7.2: Askale/Erzurum, August 2001: Participants of the BTC
information
meeting consisted of the Commander of the Gendarme and 8
village
headmen." (FFM emphasis)
Thus
the BTC information meetings clearly failed to recognise the need
for supplementary measures to ensure that project affected people
did not feel intimidated or suppressed. The FFM was very concerned
by the blatant failure of BTC/BOTAŞ to take account of aspects
of current political culture in Turkey which prevent the free expression
of critical views about a national project such as the BTC pipeline.
A village representative told the FFM that villagers had felt unable
to express their views at the meetings held. This, he explained,
was due to the fact that the BTC project information groups came
accompanied by law enforcement officials. He explained that in the
current political situation, where villagers of Kurdish ethnicity
are routinely harassed and detained by the same law enforcement
officials, nobody dared to speak up at the meetings.
As
documented in Section 1, the FFM finds that, due to the socio-political
conditions in the north-east region, there is no real prospect of
an open debate on the issue. Intimidation and harassment by the
police and security personnel ensure that many local people are
afraid to publicly voice their concerns over the project. Moreover,
the FFM’s attempts to visit more villages were curtailed by the
surveillance and tailing it experienced, itself indicative of the
human rights situation in the region
The
fear of freely expressing opinion applies also to political parties.
In the case of smaller opposition political parties, their freedom
of expression and advocacy are furthered weakened by the fear of
proscription or closure. Accordingly, the consultation process is
fundamentally flawed in that it failed to understand and take into
consideration the political agenda that operates in the area.
Local
DEHAP politicians told the FFM that nobody had consulted local branches
of the party, a critical representative of the interests of the
Kurdish community, with regard to the BTC project. They further
stated that in the region, they feel they do not have the political
freedom to voice the concerns of their voters. Whenever they call
a demonstration, even when the subject matter is the environment,
they and the participants are subjected to pressure from the police
and the state. The DEHAP regional chair said that there is no freedom
of expression in Turkey and that, although the recent Harmonisation
Laws (see Section 1) are very welcome, implementation on
the ground is yet to come. Both representatives of DEHAP interviewed
by the FFM said that the number of detentions and arbitrary arrests
had increased in recent times, that the party is under 24-hour surveillance
and that villagers are under unabated psychological pressure.
Another
local, a journalist, told the FFM that the BTC project has been
pushed through like the Bergama project and that BTC had a ‘golden
chance’ in the north-east because in that part of the country people
have been successfully silenced for decades. His newspaper, one
of the few to criticise the project, has been shut down three times.
It
is perhaps significant that the FFM was repeatedly told by those
that it interviewed that there would be a better chance for voicing
opposition in the West of the country and that the project could
be a tool for hastening the already existing migration patterns
of Kurdish people out of the north-east.
The
FFM acknowledges that due to constraints of time and particularly
of state harassment, it was only able to interview a small sample
of villages and local representatives during its visit. Nevertheless,
the consistency of accounts by villagers of intimidation and harassment,
resulting in the lack of freedom of expression, merits investigation
by the BTC Consortium and the sponsors of this project. In light
of all the aforementioned, the FFM finds that no meaningful consultation
could have taken in the north-east region of Turkey.
2.4
INADEQUACIES IN THE CONSULTATION OF WOMEN
The
FFM is very concerned that women were not adequately consulted and,
in some instances, not consulted at all. The FFM’s concern is directly
germane to the issue of consultation in that the FFM found that,
in the majority of villages visited, women held land titles or were
benefiting from the use of common land. In order to ensure effective
consultation, women - as an often-neglected group, and often-invisible
actors of local economies - are to be considered at the planning
stages of the process. Accordingly, the Public Consultation and
Disclosure Plan (‘PCDP’) states that "the PCDP aims to identify
key stakeholders and ensure adequate mechanisms for stakeholder
feedback and information sharing".
The
FFM found that the consultation process failed to comply with the
IFC guidelines on public consultation and disclosure with respect
to women on a number of counts. Specifically, the BTC Consortium
failed to:
- proactively
disseminate in a culturally appropriate manner a summary of
the project in the local language;
- consider
undertaking other traditional mechanisms for consultation and
decision-making;
- pay
particular attention to seeking out less powerful and disadvantaged
groups such as women;
- select
appropriate and effective methods of consultation that recognise
the specific needs of women;
- consult
all relevant stakeholders, including project affected women.
The
Consortium claims that there is no need for Kurdish language consultation
on the project, neither orally or in written form. Yet the FFM found
that some of the women landowners or users of land were illiterate
and thus unable to read the information distributed. Moreover, the
majority of women in Kurdish areas were only able to speak Kurdish,
not Turkish. Some villagers told the FFM that, though women were
invited to attend the public meetings and that the BTC information
group included a woman, they had no reason to attend as all the
members of the BTC/BOTAŞ team only spoke Turkish. In other
words, BTC Co.’s failure to disseminate information in Kurdish amounts
to a form of gender discrimination by language, systematically depriving
women of equal rights to access to knowledge and information about
the project. This discrimination has its roots in BTC Co.’s equation
of ethnicity with language, which the FFM regards as both theoretically
and practically flawed.
In
one village the FFM was told by a large group of villagers that
women own 10% of the land but no one had consulted them at all.
The villagers did not know whether the women had complained about
this. The FFM then met with one of the affected women and she expressed
her dissatisfaction with the compensation paid. Two other villages
told the FFM that, though there was a female representative at the
information meetings, she never asked to see the women separately
and thus they were not consulted. These examples illustrate the
flawed approach taken to consultation, notably the assumption that
the presence of a female representative is enough to ensure that
women are consulted.
In
addition, the FFM was disturbed by the lack of political representation
of women in the area and the reasons behind it. The Chairman of
a local political party told the FFM that, though their party would
wish to encourage greater political participation of women, they
are afraid because, if detained, women are at risk of sexual violence.
Thus in the north-east women are a singularly vulnerable group in
that they cannot benefit from anonymous political representation
and advocacy that focus on their specific problems and concerns.
2.5
LACK OF CONSULTATION ON THE IGA AND THE HGA
According
to the IFC’s manual Doing Better Business Through Effective Public
Consultation and Disclosure all relevant private and public
stakeholders are to be consulted on the project. The Host Government
Agreement is at the core of the BTC project and thus the FFM is
of the view that, notwithstanding the fact that they are not statutory
bodies, stakeholders should have been consulted on the nature of
the documents governing the project. In this case, the FFM finds
that consultation on the HGA is of crucial importance given that
the agreements define the rights and duties of all interested parties,
including those of project affected people.
None
of the bodies, organisations or villages visited by the FFM was
informed by project companies of the
existence or nature of the HGA and IGA. Given the crucial importance
of these agreements to Turkey, its citizens and the project itself
and the likely implications these may have on Turkey’s EU accession,
the FFM finds this omission of particular concern.
The
HGA severely restricts the nature and extent of consultation. Article
3.9(iii) of Appendix 5 provides that key stakeholders shall be notified
of the nature of the project during the establishment of the EIA
and only invited to comment after its completion. Thus it does not
impose an obligation on the BTC Consortium to involve key stakeholders
in the drafting of the EIA and in so doing it does not require the
consortium to take account of the technical expertise and research
of relevant NGOs and Turkish professional organisations. Taking
into account the intrinsically complex nature of the project, the
decision to reduce the governmental approval period from 60 days
to 30 days made it almost certain that the process was insufficient.
- The Chairman
of the Human Rights Commission of the Turkish Parliament informed
the FFM that, to his knowledge, the Commission had not been consulted
about the project and no information had been provided regarding
the agreements.
- WWF was not
consulted on the drafting or adoption of these agreements. WWF
is concerned that the HGA will constrain the application of EU
law in the future and that there will be no point for them in
lobbying the Government on environment issues as they are bound
by the HGA.
- The Chamber
of Environmental Engineers was not consulted during the drafting
of either of these agreements. They are worried that such important
documents for the future of Turkey had gone unnoticed and without
the consultation of the Turkish public at large. This lack of
consultation, they said, is of crucial relevance given that the
HGA overrides existing environmental legislation and might create
a bad precedent for the future to which the government will not
be able to object.
The
FFM notes that the generalised failure to ensure proper consultation
on the EIA, the RAP and the HGA is neither in the interests of those
affected nor of the project developers. On the contrary, there is
a strong possibility that the failure to consult will engender resentment
of the project and act against its smooth implementation and future
operation, in addition to incurring reputational risks for the companies
that form the BTC Consortium.
Section
3
LAND
EXPROPRIATION, COMPENSATION AND THE
RESETTLEMENT
ACTION PLAN
The
BTC pipeline would affect 3,105 hectares of land in Turkey. Under
the Host Government Agreement for the BTC project, the Government
of Turkey has undertaken to obtain the requisite land rights for
the project through an expropriation process that conforms to Turkish
law and to appoint a Designated State Authority (DSA) to undertake
the land acquisition process. BOTAŞ, the state-owned pipeline
company that would build the pipeline under a Lump Sum Turnkey Agreement
(LSTA) signed in 19 October 2000, has been appointed the DSA. The
Turnkey Agreement forms part of the HGA and requires that the land
acquisition procedures are compliant with OD 4.30, the World Bank
Group’s policy on involuntary resettlement. All the expropriation
procedures will be carried out by BOTAŞ’ Land Survey and Expropriation
Department "on behalf of BTC Co."
However,
it has recently been suggested in the Turkish press that BP has
written to the Turkish Prime Minister, Tayyip Erdoğan, giving
a detailed critique of BOTAS’s alleged failings, which include not
completing the appropriation process rapidly enough, administrative
inefficiency and a superfluity of bureaucracy, and a tendency to
undertake obstructive corruption allegations when, "The consortium
sufficiently examines allegations of corruption regarding BTC."
According to these suggestions, BP has threatened to withdraw the
BTC contract from BOTAS and award it elsewhere.
Although
no-one would be required to physically move from their homes or
villages as a result of the project, some 10,117 households, affecting
30,000 people, would lose the use or ownership of land, and suffer
"economic displacement". Under OD 4.30, the project developers
must therefore produce and implement a Resettlement Action Plan
(RAP) aimed at ensuring that those affected by the project are no
worse off than prior to the project and preferably better off.
The
previous Fact-Finding Mission (FFM) to Turkey in July 2002 found
that BTC/BOTAŞ was failing to apply the land expropriation
and compensation required under the HGA and LSTA in all of the villages
that the FFM visited (see Box: Findings of the July 2002
Fact Finding Mission). Moreover, the FFM heard evidence that strongly
suggested that such failures were common along the entire pipeline
route. The FFM found that, in addition to violating OD 4.30, the
project also violated the World Bank safeguard policy on Indigenous
Peoples, which covers the treatment of ethnic minorities. The FFM
was of the view that, if the project went ahead as then pursued,
there would be strong grounds for a legal challenge under the European
Convention on Human Rights and other international human rights
instruments.
Since
the first FFM reported, the BTC consortium has produced a full RAP
for the project, IN which the consortium claims to comply with requirements
of the HGA, Turkish Law and the relevant World Bank Group standards.
This section reviews:
- The provisions
of the RAP against the provisions of the Host Government Agreement
(HGA) for Turkey and the Lump Sum Turnkey Agreement agreed between
the BTC Consortium and BOTAŞ;
- The extent
to which the project developers have remedied resettlement-related
problems identified by a previous FFM in July 2002;
- The implementation
of the RAP against relevant World Bank group/IFC standards and
Turkish domestic law.
The
FFM found that significant progress had been made towards resolving
several of the issues identified by the previous Fact Finding Mission,
notably on the issue of compensation for land users without title.
However, such progress is restricted to the central section of
the pipeline route (Sivas to Erzurum). Moreover, throughout the
pipeline route, the FFM found widespread evidence of major shortcomings
in the design and implementation of the RAP.
These are set out in detail in the rest of this section.
In summary:
- There are
still major problems with the compensation of customary owners
in the north-east, many of whom have been told they have to obtain
their titles, at their own cost, in order to be eligible for compensation.
- Understanding
of compensation arrangements is poor, and many landowners only
found out which part of their land they would lose when they went
to the bank to collect their compensation. Non-Turkish speakers
have suffered the most through lack of information, as project
companies have not provided Kurdish speakers.
- The RAP’s
provisions on negotiating land prices appear to be in conflict
with the requirements of Turkey’s Expropriation Law, placing the
project in potential breach of the HGA.
- By failing
to get a measure of the true rather than the registered market
value of land, BTC is consistently underpaying and failing to
provide a fair price, despite claims to
the contrary. According to villagers interviewed by the FFM, not
a single payment was as high as the budgeted average in
the RAP, and most were about half that level.
- Villagers
interviewed by the FFM suggested that they had been consistently
misinformed about their opportunities for redress if they disagreed
with the compensation figure or process. Some were told they were
not entitled to go to court, others that they could go, but it
would be expensive and time-consuming. Under Turkish law, the
cost of ensuring due process should be borne by the expropriating
authority.
- Although
a RAP fund has been set up to compensate those without land title,
in compliance with the requirements of OD 4.30, no-one interviewed
by the FFM had any knowledge of the Fund. As a result, those eligible
for compensation through the fund – often the poorest in the community
– are not in a position to apply for compensation. The RAP Fund,
in practice rather than theory, simply does not exist for people
in the region.
- Similarly,
it is highly improbable both for practical and cultural reasons
that the majority of tenants will receive any form of compensation,
which will be given to their landlords and which they are in no
realistic position to request. In any case, as tenants will only
be compensated for assets, of which almost by definition they
have very few, rather than loss of income, the amount of money
involved would not be enough to restore their socio-economic position
even if they were able to obtain it.
- This is part
of a wider phenomenon of BTC’s systematic failure to compensate
for loss of income rather than for immediate assets lost. This
includes failure to compensate for loss of ongoing productivity,
failure to pay the full replacement cost of land and failure to
compensate for economic opportunities foregone and investments
precluded by the pipeline and its construction processes.
The
FFM is thus disturbed that the majority of the protection mechanisms
that BTC has claimed to ensure that all project-affected people
are not negatively impacted by BTC
are either unknown to local people, inoperative, ineffective or
not being applied by BTC staff. It is of particular concern that
BTC Co has claimed credit from IFIs and other potential project
funders for policies which in practice do not exist.
Whilst
some of these shortcomings (for example, the lack of knowledge about
the RAP Fund) may be addressed through improvements to the RAP,
the FFM is convinced that the political repression evident in the
north-east section of the pipeline route renders fair negotiation
over compensation currently impossible. The FFM finds this a further
compelling reason for both the project developers and the international
financial institutions to impose a moratorium on the project.
------------------------------------------------------------------------------------------------------------
BOX:
Findings
of the July 2002 Fact Finding Mission
In
July 2002, a previous Fact-Finding Mission travelled the length
of the pipeline route from the site of the Ceyhan pipeline terminal
to Erzurum. The Mission interviewed villagers from 8 communities
affected by the pipeline in order to assess the extent to which
affected communities had been informed about the social and environmental
impacts of the project and of their legal rights with respect to
damages and compensation. It found widespread evidence of inadequacies
and failures in both the design and the implementation of the consultation
and compensation procedures for the project. Specifically:
- Although
the BTC consortium had committed itself to paying compensation
to anyone affected by the project, villagers had been told by
BTC/BOTAŞ that only formally registered landowners
would be compensated. In effect, many of those whose land would
be affected by the pipeline would be deprived of any compensation
whatsoever.
- Contrary
to claims by BTC / BOTAŞ that the value of lost assets "would
be made in accordance with fair market value", the price
paid for land lost was likely to be well below the land's market
value.
- In several
of the villages surveyed by the FFM, BTC / BOTAŞ had not
spoken to landowners. There was thus considerable worry and uncertainty
about whether they would be compensated for loss of their land.
- In all villages
visited, there was a complete lack of knowledge about possible
recourse in the event of unexpected damage.
- BTC / BOTAŞ
had given no indication that they would be willing to compensate
for losses incurred to further land, resources and infrastructure
that would be damaged outside the immediate pipeline corridor.
------------------------------------------------------------------------------------------------------------
3.1
CONFLICTS BETWEEN THE RAP AND THE HGA
As
noted above, the project agreements reached between Turkey and the
BTC Consortium require that the procedures for acquiring land rights
for the project comply with Turkish law and with the World Bank
group’s standards for involuntary resettlement (OD 4.30).
The
FFM was unable to review the full range of Turkish laws of relevance
to compensation and resettlement. However, it compared the RAP against
the recently-amended Expropriation Law and was disturbed to find
striking inconsistencies with regard to the RAP’s provisions for
negotiating land values and consequent levels of compensation.
Article
8 of Turkish Expropriation Law states that "the administration
[in this case, BOTAŞ] shall assign one or more than one reconciliation
commission … for the purpose of executing and completing the purchasing
works through bargaining over the estimated cost and through
barter… the bargaining negotiations shall be held
on a date designated by the commission." (Italics added)
Under
Turkish law, bargaining and barter are thus central to the process
of negotiation over land values. This would accord with normal usage
of the word "negotiate", as defined by the Oxford English
Dictionary: namely, "to confer in order to reach an agreement".
By contrast, the RAP explicitly rules out any bargaining or bartering
in the negotiation process. In its clearest explanation of the
procedure to be adopted, it states:
"The
Negotiations Commission begins discussions with landowners based
on the range of land values established by the Valuation Commission.
The "negotiation" process does not consist of bargaining.
Indeed, as mentioned in Chapter 2, the negotiation commission
has no room for bargaining. Rather, this commission explains
the basis of valuation to affected communities and each of the
affected titled deed owners. It provides detailed information
obtained from each source specified under the Law and shows
how valuation decisions have been reached."
This
entirely top-down approach flatly contradicts the impression BTC
Co / BOTAŞ have created that the negotiating of compensation
is a collaborative, consensual process. In addition, whilst the
Expropriation Law requires that the landowner should not be told
of the deemed value of their land, the RAP stipulates precisely
the opposite. Describing the role of the RAP’s "Negotiation
Commission", the RAP assigns the Commission with three responsibilities,
two of which would appear to be direct breach of the Expropriation
Law’s provision: namely:
- "To
inform the landowner about the value of the land as determined
by the Valuation Commission; and...
- "To
demonstrate that the proposed land valuation is fair
and detail the appraisal criteria for the individual parcel."
Moreover,
the Commission is only assigned a responsibility to negotiate the
proposed land price "in the interest of averting a court case".
This suggests that "negotiation" is a last resort, where
a court case is threatened, rather than being the required means
of agreeing a price. In this regard, the FFM finds that the RAP’s
"negotiation" procedures constitute a direct encouragement
to impose prices where possible.
The
FFM finds the exclusion of "bargaining" from RAP’s
provisions on negotiations to be in potential conflict with Turkey’s
Expropriation Law and consequently in breach of the HGA which requires
compliance with the Expropriation Law. As documented below,
the breach is not only on paper: the practice on the ground is clearly
to impose land values rather than negotiate them. The FFM recommends
that the IFC and other international financial institutions should
refuse funding for the BTC pipeline until they are assured that
the RAP conforms to Article 8 of the Expropriation Law, both on
paper and in practice.
3.2 DEFICIENCIES
IN THE IMPLEMENTATION OF THE RAP
A
key remit of the FFM was to review the implementation of the RAP
against its stated objectives. Although some progress since
the previous FFM in July 2002 was recorded, the FFM found that BTC
/ BOTAŞ is still violating many of the project’s own
guidelines, as described in the RAP. Such violations, coupled with
fundamental problems in the design of the RAP itself, places the
project in continuing breach of World Bank group/IFC safeguard policies
and domestic Turkish law.
The
FFM notes that the support of OECD Export Credit Agencies would
require that the project complies with host government standards.
Potential breaches of Turkish law relating to land acquisition and
compensation are therefore particularly problematic for the project,
since the Host Government Agreement requires compliance with the
Turkish Expropriation law. Since the HGA constitutes the prevailing
local law governing the project, any breaches of the Expropriation
Law, if upheld, would constitute grounds for challenging any export
credits from OECD countries. Breaches of the World Bank’s Involuntary
Resettlement policy (OD 4.30) would similarly place the project
in conflict with OECD rules, since compliance with OD 4.30 is required
under Section 8.42, Appendix A of the Lump Sum Turnkey Agreement,
which forms part of the HGA.
The
FFM’s findings are detailed below.
3.2.1 Compensating
customary land-owners and users
RAP
objective: "Ensure that all affected parties are compensated
and assisted in restoring their livelihoods... whether these
lands are formally or customarily owned".
Both
Turkish law and OD 4.30 require that all users of private land should
be compensated.
The
FFM found that in the central section of the pipeline (Erzurum-Sivas),
significant progress had been made towards resolving the issue of
compensation for land users without official title to private land.
In three of the six villages that it surveyed in this region, the
FFM was told that – while there had indeed previously been a problem
– BTC / BOTAŞ had now agreed to pay compensation to all users
of private land affected by the project. The Mission also confirmed
that BTC was making significant efforts to contact landowners who
were no longer resident in the pipeline corridor, in order to compensate
them.
The
FFM welcomes the steps that have been taken to respond to the concerns
raised in the first Fact-Finding Mission, in relation to this issue.
However, it notes with considerable disquiet that the same problem
appears to remain unresolved in the north-eastern section of the
proposed pipeline (Posof-Kars). The FFM interviewed a number of
landowners without official title: all reported negative experiences
and lack of clarity. The failure to resolve problems arising over
land titles in the north-eastern section of the pipeline route is
particularly disturbing, given that the vast majority of households
in the north-east lack formal title to land – respectively 87% and
68% in Kars and Ardahan provinces, compared to an average of 32%
along the whole route.
Although
Turkish law stipulates that it is the responsibility of BOTAŞ
to regularise land titles at its own cost - and, indeed the RAP
commits to do so - most of the villagers who the FFM interviewed
in the north-east had been told to obtain their titles themselves,
at their own cost, in order to be compensated. The only exceptions
were villagers who insisted that BOTAŞ arrange their
compensation without titles.
The
FFM deems this a clear violation of the RAP, which stipulates that
BTC / BOTAŞ will pay the legal costs of expropriating land
from landholders who do not have legal title. The failure to follow
this procedure would also appear to put the project in potential
breach of Article 19 of the Turkish Expropriation Law, which specifies
a process for compensating landowners who lack title without their
having to go to court to register their land.
Such
practices would appear to constitute discrimination against those
without land title. As such, they would contravene Clause 17
of World Bank Operational Directive OD 4.30, which states: "The
objective is to treat customary and formal rights as equally as
possible in devising compensation rules and procedures." The
FFM also notes that the discrimination against land users without
title impacts disproportionately on women. One villager reported
that it was worst for widows, whose land is registered in their
husbands’ names. "BOTAŞ told them to go to court to get
titles. This costs a lot, so the women are helpless".
Several
villagers were very angry that they were being asked to pay court
costs in order to be eligible for compensation. In one village,
it was reported that several landowners had been to court to obtain
their official titles – at considerable cost. Some villagers are
sticking to their rights, however. One told the FFM, "I am
determined that I will get my payment without having to pay for
it. I am ready to fight with BOTAŞ and not give them my land".
Many
villagers, however, are not in a position to insist on their rights.
In the north-east, there is considerable harassment of Kurdish people
by the state Gendarmerie (see Section 1): the FFM considers
it highly probable that the fear of such harassment actively discourages
people from taking on a powerful state institution such as BOTAŞ.
The disempowerment of villagers is further compounded by a lack
of information as to their rights and how they can protect them.
RAP
plays down importance of compensation
Based
on the accounts of the people it interviewed, the FFM disputes the
claim in the RAP by BTC that "the level of expropriation is
substantive in terms of total hectares, but is modest in terms of
the impact on each family", a claim it bases on the observation
that only 19% of the land area of affected plots will be used in
construction. Those interviewed by the FFM strongly indicated that
they would be significantly impacted by the project. BTC’s observation
ignores both the impact on a plot of bisecting it (so that the sub-plot
either side of the corridor becomes too small to work), and the
often marginal and subsistence nature of production in the rural
areas crossed by the pipeline – such that 19% is in fact a substantial
proportion.
The
RAP further claims that on average only 0.5% of household income
would be lost due to the project. Although the FFM does not have
sufficient data to assess the estimate, it does not accord with
the extent of concern expressed by all of the FFM’s interviewees.
The FFM speculates as to whether this average is skewed by a number
of much wealthier landowners, who would be less impacted, or whether
there were even errors in its methodology of calculation.
Whatever
the true picture of the proportion of people’s incomes lost to the
pipeline project, this should emphatically not be taken as a justification
for the lack of diligence in applying the compensation procedures
outlined below, nor for the below-market rate of compensation offered.
Source:
RAP Turkey Final Report, section 4.12, page 4-25, November 2002
3.2.2 Understanding
of implementation arrangements
RAP
Objective: Establish "a process of consultation with affected
populations, and with local public and civic organisations [to]
maximise understanding … [of] implementation arrangements for resettlement,
expropriation and compensation."
The
FFM found only one Muhtar who had a good understanding of the compensation
and expropriation process, which he explained almost exactly as
it is described in the RAP – all other interviewees reported the
compensation procedures very differently from the manner in which
they are reported in the RAP. The Muhtar was also the only one whose
villagers had been given the opportunity to negotiate on price,
and the only one who thought the price was fair; indeed, the only
one who was broadly happy with the compensation regime. The FFM
notes that same muhtar has expressed strong criticisms of the compensation
procedures when the previous FFM visited him in July 2002.
Elsewhere,
the Mission found understanding of the land acquisition and compensation
process among landowners and users was disturbingly slight:
- Many villagers
reported that the compensation procedures were only explained
to them when they went to receive their compensation. In one village,
landowners were only informed of the price they would be paid
– and even which parts of their land would be expropriated – as
they attended the payment offices to claim their compensation.
A local journalist and political party representatives told the
FFM that such cases were widespread.
- Although
the RAP requires "transparency in the valuation of assets",
the FFM found that only one of the eight villages it contacted
had a good understanding of how compensation levels were calculated.
Elsewhere, some villagers who had specifically asked BOTAŞ
about valuation procedures knew that there had been a commission
of some sort, but did not know how it arrived at a value, nor
what the process for expropriation was, nor their rights to challenge
any offer.
- While the
RAP reports that 30,000 brochures (the Guide to Land Acquisition
and Compensation) would be sent out to landowners and users along
the pipeline route, the FFM found many examples of villagers who
had not received the brochures: others who had, reported the text
to be too technical to understand. Since the FFM mainly visited
Muhtars, it suspects the receipt and understanding of the GLAC
may be even worse for the general population. A resident of another
village told the FFM that the only consultation meeting was far
too long and technical for him to understand or take in the information.
"Some people spoke for hours, and it wasn’t very useful.
It would have been better to have more, shorter meetings".
- The RAP also
commits BOTAŞ to ensuring that "people are informed
of their rights under the amended [2001] Expropriation Law and
informed that their rights will not be jeopardised."
This will be achieved "primarily through preparation
and distribution of summaries of the relevant Laws to both resident
and absentee owners". The FFM found no-one who was appraised
of the amendments to the law, or who understood their own rights.
- The FFM found
no evidence of special efforts to consult with, or explain arrangements
to, women landowners. In one village, this was because BTC / BOTAŞ
staff never asked to talk to the women, and the local men never
offered to make suitable arrangements. In two Kurdish villages,
BTC / BOTAŞ did not bring Kurdish speakers, and since many
women and elderly people do not speak Turkish, they did not see
any point in coming to the meeting.
In
the FFM’s view, such deficiencies place the project in breach of
Clause 14(b) of OD 4.30, which states that "Compensation
is facilitated by publicising among people to be displaced the laws
and regulations on valuation and compensation."
In
addition, by failing to consult Kurdish speakers at all village
meetings in Kurdish areas, and by not specifically consulting women,
the project violates Clause 8 of OD 4.30: "Particular attention
must be given to ensure that vulnerable groups such as indigenous
people, ethnic minorities, the landless, and women are represented
adequately in such [consultation and participatory planning] arrangements."
The
FFM also notes that the project fails to follow the "management
principles" set out in the IFC’s Doing Better Business through
Effective Public Consultation and Disclosure – A Good Practice Manual,
which the BTC Consortium states it has taken into account when drawing
up the RAP. The Manual states that companies should "aim
to provide information to the public as early as possible during
the planning and implementation of a project, except in cases where
such disclosure would materially harm the interests of the company"
and "provide information in a form that is readily understandable
and meaningful to project-affected people".
The
IFC principles also state that local languages and dialects, clarity,
cultural sensitivity, gender, age, ethnicity and literacy levels
should be taken into account. The lack of Kurdish language presentation
and discussion with affected Kurdish women landowners is clearly
a direct violation of this guidance.
3.2.3 Negotiation
of compensation deals
RAP
Objective: "Undertake land acquisition through negotiation
with affected landowners, users and occupiers"
As
noted earlier, the RAP’s approach to "negotiation" currently
conflicts with the approach set out in Turkish law. The FFM has
also found that, on the ground, Turkish law is also being breached
in the implementation of the land acquisition procedures.
The
FFM recognises that, for a project as large and complex as BTC,
no crude or simplistic approach to compensation mechanisms will
be adequate: if the overall goal of BTC is to restore or improve
the livelihoods of those affected, compensation issues must be approached
with as much sophistication and rigour as engineering, economic
and financial issues.
The
previous FFM report raised concerns that compensation agreements
reached in secret between BTC / BOTAŞ and individual landowners
were likely to lead to tensions between neighbours and within communities.
It therefore recommended greater collectivisation of bargaining
procedures, involving Muhtars in negotiations, and at the very least
some transparency in the process.
BTC
/ BOTAŞ has since changed its approach to one of common fixed
pricing of land, mostly jettisoning negotiation altogether. The
result is that villagers no longer feel jealousies over their neighbours’
treatment: instead they know that everyone in their village
is being treated unfairly. The FFM believes that this situation
is in fact far worse than that which was expected by interviewees
of the first FFM:
No
Negotiation
Of
the eight villages whose members were interviewed by the FFM, only
one reported that BTC / BOTAŞ had actually negotiated on the
compensation price to be paid. Six stated that the price had been
dictated, and one did not know whether there had been a negotiation.
One interviewee commented that ordinarily land values are always
determined by negotiation and it was widely felt that negotiation
would have resulted in a fairer price being offered. Some villagers
were angry that no negotiations had taken place; others were resigned
to the fact.
One
local journalist in the north-east commented that "The pipeline
agreement is like a war decision. They just take land without even
consulting people." A number of villagers reported that they
had not been told by BTC / BOTAŞ which precise parts of their
land would be lost until compensation payments were paid, giving
them no opportunity to negotiate on the basis of the quality of
the land affected.
High
Transaction Costs for Affected People
A
further problem is the cost to landowners of participating in the
process of negotiation and payment. The legal costs incurred by
landowners are referred to above and below, but there are further
costs related to transport and loss of work time.
The
RAP states, "landowners will not be obliged to visit the local
DSA/BOTAŞ branch. To facilitate discussions, the relevant DSA/BOTAŞ
officers will visit each affected village." However, in all
villages which the FFM visited, villagers had been obliged to travel
- at their own expense – up to 40 kilometres to obtain their compensation
from the bank, BOTAŞ office or other agency. Although the RAP
commits that "the agency [BOTAŞ] facilitates people’s
transport to land registration offices", in no
case did this take place.
One
Muhtar was particularly aggrieved that members of his village had
been told a date to come to claim their compensation; only when
they arrived were they told that the date had been postponed, and
they would have to come back again the following week. Not only
did these villagers have to pay for a second trip, mostly they lost
two days’ work rather than one.
3.2.4 Fairness
of price
RAP
Objective: "Pay fair compensation based on market value,
full replacement cost or loss of income, as the case may be."
In
the majority of villages it surveyed, the FFM heard complaints over
the fairness of the compensation received and their failure to reflect
either sale values or full replacement costs, in contravention of
OD 4.30. The FFM also found evidence that the compensation payments
being made by BOTAŞ were well below those budgeted.
Unfair
Payments
Of
the eight villages whose members were interviewed by the FFM:
- five said
the compensation price was unfair;
- one said
it was fair;
- one did not
express an opinion; and
- one did not
comment on the value of compensation itself but stated that it
was unfair if damage to land outside the 28-metre corridor was
not compensated.
However,
the village that said the price was fair qualified this view by
adding that its fairness was dependent on the land being quickly
restored to its former quality after construction. The FFM’s interviews
with Turkish environmental experts suggested that this was very
unlikely to be the case, based on their assessments of the EIA,
of pipeline construction procedures and of the Turkish environment.
Indeed, the East Anatolian Natural Gas Pipeline – which was also
built by BOTAŞ along much of the same route as BTC (between
Erzurum and Sivas), in 2000-2001 – left the land completely unusable,
and badly scarred.
The
FFM found particular anger over compensation arrangements in the
north-east section of the pipeline. In one case, it was stated to
the FFM that the low level of compensation was a deliberate attempt
to force villagers to migrate to the cities. To compound the problem,
early in the project BTC / BOTAŞ told landowners that the compensation
would be generous, and thus raised their expectations. According
to one interviewee, "At the public meeting, they said our land
would gain in value from this project, and we would be paid very
good compensation – more than we could imagine… Villagers asked
how much compensation would be paid, and they said enough to satisfy
you – you will not lose out… This all made me think I would like
to buy a tractor with the compensation money. In reality, of course,
there was nothing like enough".
Failure
to Reflect Sale Value of Land
The
FFM is concerned that BTC / BOTAŞ appears to have taken the
officially registered price as the market value of the land. Indeed,
the eight specific factors taken into account in valuation, as specified
in the RAP, include alongside the physical characteristics of the
land, the following four that relate to the registered value:
(iv)
tax statements;
(v)
an estimate made by official authorities;
(vii)
the sales amount of similar land sold before the date of expropriation;
(viii)
official unit prices.
Similarly,
five of the six expert institutions that the Valuation Commission
is recommended to consult are likely to be in possession only of
registered prices: title deed registry offices, municipalities (based
on tax records), state property directorships, state authorities,
and real estate agencies.
Indeed,
the FFM consistently found that land is registered at below the
real value, as is common practice, because of excessive taxation
levels. In no case did the FFM find an interviewee who had registered
land at more than 50% of its value, and 10-20% was more common.
Unsurprisingly,
the majority of villagers to whom the FFM spoke made it clear that
the price being paid for both the 28-metre corridor and the 8-metre
corridor was significantly below what they would obtain if they
the sold the land to neighbours. In the north-east, the figure given
was 5 million lira per square metre in a normal land sale as compared
to 1.0-1.5 million lira being paid for the 8-metre corridor. Many
villagers pointed that the declared price for land sales was always
far below the actual price paid by villagers because of high taxes
levied by the state.
Failure
to Pay Full Replacement Cost
Although
the RAP states that "in assessing the value of the asset...
full replacement cost is the principle", the FFM found that
this principle is being routinely flouted. Irrigated land, for example,
is not being compensated at higher price than non-irrigated land.
Many of those interviewed were aggrieved by this practice, which
they found grossly unfair. Indeed, the issue was raised (unprompted)
by members of six of the eight villages surveyed. The FFM finds
BTC / BOTAŞ’ failure to recognise the difference between irrigated
and non-irrigated land in its compensation payments surprising,
given that an official distinction is made within Turkish law. It
also deems it to be a breach of the RAP and of OD 4.30, which states,
"Displaced persons should be compensated for their losses at
full replacement cost".
No
compensation for loss of ongoing productivity
The
RAP admits that however meticulous its restoration of the 28-metre
construction corridor, productivity losses will occur, affecting
the land well beyond the completion of construction activities –
for which it estimates at "a minimum 10% lifetime productivity
loss". However, in no village visited by the FFM had this long-term
productivity loss been explained; instead "full restoration"
was promised. The RAP also claims: "In the calculation of the
compensation levels for the 20-metre corridor that will be returned
to people, this factor will be taken into account". This is
contradicted by the FFM’s own findings: compensation had not been
offered for this ongoing loss of productivity in any of the villages
it surveyed, only for losses during the period of construction.
In one case, one year’s crop profit was offered, in another (the
village visited by the first FFM), three years’.
Payments
Below those Budgeted
The
RAP gives an average budget payment for permanent expropriation
(8-metre corridor) of $1.49 per square metre of private land, or
2.5 million Turkish Lira. In no case did the FFM find a landowner
who had been paid this much. In six of the villages visited by the
FFM, the compensation payments reported by villagers were: 1.25m,
1.25m, range 1.1-1.3m, range 1.0-2.36m, 1m and 1.3m lira. Assuming
this to be a reasonably representative sample, the FFM is deeply
concerned that not a single payment was as high as the budgeted
average, and most were about half that level. The FFM recommends
that potential funders obtain an explanation from BTC / BOTAŞ.
Discrimination
against users of customarily-owned land
A
similar calculation to that above shows that the average budgeted
payment for customarily-owned land is $1.13 / sq m, or 1.9m lira,
compared to $1.49 = 2.5m lira for titled land. The FFM sees no demographic
reason why customarily-owned land should be less valuable than formally
titled land. The FFM is therefore concerned that there is discrimination
against customary owners in price, on top of the problems outlined
above. This will impact disproportionately on the poor and on
the residents of Kars and Ardahan provinces, where there is a larger
Kurdish population. The FFM notes that the difference in budgeted
level of payment between formally and customarily owned land is
also in violation of Clause 17 of OD 4.30, which states, "The
objective is to treat customary and formal rights as equally as
possible in devising compensation rules and procedures".
Engineering
Consent
The
FFM is particularly concerned that at one point in the RAP, BTC
seems to be more concerned with convincing people that they are
receiving a fair price, than with ensuring that the arrangements
are indeed fair:
"DSA/BOTAŞ
… will need to have special training and procedures for its
field staff to emphasise a positive, relevant, objective and
individual approach to assessing compensation levels and beginning
the negotiation process. This is particularly important at the
beginning since the tone and character of first land and asset
acquisition attempts will become rapidly known across the affected
provinces. If plot owners feel that DSA/BOTAŞ is sensitive
to owner concerns, the process will certainly go better than
if plot owners view DSA/BOTAŞ as unresponsive and unfair.
If the first compensation offers from DSA/BOTAŞ are seen
as fair and relevant to individual situations, plot owners will
be more willing to avoid the court process."
It
is not only that BTC Co. has to be "seen as fair"; more
importantly, the company must ensure fairness in all its
dealings with those affected by the project. The RAP states that
BTC / BOTAŞ staff should be, "assuring people that valuation
is done for each individual plot." However, the RAP is silent
as to the mechanisms by which this assurance is to be turned into
reality. The FFM’s findings indicate conclusively that valuation
of individual plots of land has not been the norm along the pipeline
route.
3.2.5 Mechanisms
of Redress
RAP
Objective: "provide straightforward avenues for people
to lodge a complaint about the project and obtain redress"
Although
BTC claims to have established two complaint and grievance procedures,
none of the villages surveyed by the FFM knew anything about them.
The FFM also received evidence of major problems faced by villagers
seeking to challenge compensation payments in the court and of breaches
of both OD 4.30 and the Turkish Expropriation Law in the handling
of disputes.
No
arbitration mechanisms for challenging compensation payments exist
outside of the courts. The RAP states that, in the event of dispute,
it is up to BOTAŞ to apply to the court for a judgment, a procedure
that accords with the Turkish Expropriation Law. The RAP also states:
"Costs of due process are borne by DSA/BOTAŞ, not by affected
people". Similarly, the IFC Handbook for Preparing a Resettlement
Action Plan, which the BTC Co states it took into account when
drawing up the RAP, requires "that the project sponsor ensure
that procedures are in place to allow affected people to lodge a
complaint or claim (including claims that derive from customary
law and usage) without cost and with the assurance of a timely and
satisfactory resolution of that complaint or claim."
Disturbingly,
the FFM heard evidence that suggests a number of misapprehensions
have arisen in the minds of those to whom BTC / BOTAŞ has spoken,
namely that:
- Villagers
did not have the right to go to court.
In
fact, Article 14 of the Turkish Expropriation Law Article 14 clearly
states that a landowner has the right to challenge the expropriation
or the compensation payment.
- Whilst the
court option was theoretically available, the process would take
many years;
This
conflicts with Turkish Expropriation Law, which requires the whole
court process to be completed within 100 days.
- Any court
case would have to be paid for by the villagers so would it not
be worth their while to take proceedings.
All
but one interviewee who discussed the court option told the FFM
that landowners would have to pay the legal costs and initiate
the proceedings themselves; the exception thought that legal fees
would not be charged, but that if the case were successful a large
chunk of the compensation payment would go to the lawyers. In
fact, Article 29 of the Expropriation Law states: "It shall
be the administration executing the expropriation to bear the
allowances of the court officials under Article 10, the remuneration
of the experts assigned by the court and of the headman as agreed
by the court as well as the title deed fees under Article 15 and
all other expenses required by this Law."
Such
misapprehensions are clearly a cause for substantial concern, both
in their arising and in their currency. The Turkish Resettlement
Law clearly sets out the rights of those affected by the project
to redress through the courts at the expense of BTC / BOTAŞ.
The FFM also notes that, if villagers are indeed to be charged court
costs, this would not only be a potential breach of the Expropriation
Law but also of OD 4.30, since such a practice would clearly discriminate
against the poorer sections of the community.
The
RAP acknowledges many of the local people it surveyed were concerned
about having to pay legal costs. "Despite the provision that
legal costs will be borne by the expropriating agency, people also
feared that the real costs of them going to court would be high."
However, the RAP does not answer these fears, nor any of the other
points listed in the RAP as raised by its interviewees. The FFM
believes that the very fact of concerns being raised by people on
the ground should have suggested to BTC that there were grounds
for investigation, especially given the seriousness of the complaints.
The FFM recommends that the International Financial Institutions
investigate whether BOTAŞ and BTC Co. are complying with their
agreements and take immediate steps to bring the project into line
with World Bank Group/IFC guidelines and Turkish domestic law should
any infractions be found to have occurred.
The
FFM also finds that the issue of ultimate legal liability for infringements
of the RAP is ambiguous. It recommends that the International Financial
Institutions and the BTC Co. clearly sets out the responsibilities
of the different parties to the various agreements and the avenues
that can be used to obtain redress against each liable party.
3.2.6 Common
land and the RAP Fund
RAP
Objective: Establish "a RAP Fund, administered by BTC Co,
to ensure fair compensation to those groups denied compensation
by the Turkish Expropriation Law"
1,067
hectares of publicly-owned or common land would be used in the construction
corridor (38% of the total land used by the pipeline). The RAP acknowledges
that there is a discrepancy between existing Turkish law and the
World Bank’s guidelines on resettlement: unlike the Bank, Turkish
law does not require compensation for individual and community users
of public land, for example. However, BTC Co has undertaken to devise
"mechanisms" to remedy these differences. Specifically,
it has set up a RAP fund to compensate users of public lands.
The
RAP claims that, "Implementation arrangements for the [RAP]
fund will be determined during the first stages of RAP implementation."
It further requires that "people are aware of the RAP fund.
This will be achieved through providing information to the village
administration of directly affected communities."
The
FFM interviewed residents of three villages with substantial amounts
of common land. All of them believed that no compensation at all
was available for common land, and had specifically been told so
by BTC / BOTAŞ. None of them (including a Muhtar interviewed
in one of these cases and a Deputy Muhtar in another) had any knowledge
of the RAP Fund, and stated that they had only heard of it from
the FFM.
Even
if the RAP Fund were publicised and provided, the amount of compensation
would be very low. As noted above, the average compensation payment
for private land is $1.49 = 2.5m TL per square metre. BTC Co has
allocated $2 million for the RAP Fund, to compensate mainly for
the loss of 319.8 hectares of permanently acquired (in 8-metre corridor)
public land. Even if no compensation is paid for temporarily lost
public land (in the 28-metre construction corridor), the average
compensation available for the 8-metre corridor is $0.63 = 1.1m
TL per square metre, which is clearly not enough money to replace
the land.
Many
interviewees said that poorer people relied on common land for grazing
livestock, as poorer people did not have access to land of their
own. Thus, the loss of common land without compensation will impact
particularly on poor people.
By
impacting more severely on poor people through not adequately compensating
common land, the project fails to comply with Clause 3(b) of World
Bank Policy OD 4.30, which states that "Particular attention
should be paid to the needs of the poorest groups to be resettled."
The
project’s failure to ensure that affected land users know about
the RAP Fund inevitably undermines its implementation, since money
will only be made available to those who apply directly for funds.
In the FFM’s view, this mean that the project remains in violation
of Clause 15(c): "Some types of loss, such as access to … fishing,
grazing, or forest areas, cannot easily be evaluated or compensated
for in monetary terms. Attempts must therefore be made to establish
access to equivalent and culturally acceptable resources and earning
opportunities."
3.2.7 Tenants
RAP
Objective: Inform "all directly affected communities in
advance so that tenants can make clear cut compensation sharing
agreements with owners when drawing up future leases"
18%
of plots of land affected by BTC (1,618 out of 8,987) are cultivated
by tenants. The RAP correctly highlights concerns over tenants losing
out on compensation: "The key concern of RAP does not have
to do with tenants’ rights, rather [with] complicated tenancy arrangements.
Additional issues may even arise from the fact that the tenants
of today may not be the tenants of next year".
To
address this concern, BTC claims that BOTAŞ is informing "all
directly affected communities in advance so that tenants can make
clear-cut compensation-sharing arrangements with owners when drawing
up future leases." In addition, "the disclosure documentation
distributed during the third week of September invites all tenants
/ sharecroppers to obtain a letter from the owners to somewhat formalise
the tenancy arrangements and allow them to be compensated for the
crops on the land at the time of the entry of the construction teams
to the relevant plots."
The
FFM views the RAP’s proposed mechanism for resolving the complexities
of tenancy arrangements as unrealistic:
- According
to the RAP, tenants will not be compensated for their loss of
income, nor will access to other land from which to earn a livelihood
be ensured. Rather, the concrete mechanisms outlined in chapter
6 of the RAP make it clear that tenants will only be compensated
for their assets, such as crops which have already been
planted, and which are lost due to construction: "Their entitlements
are limited to affected crops, trees (if planted by tenants) and
structures (including informal irrigation works) that might have
been built by tenants". This payment is conditional on the
tenants obtaining a letter from the owners, which states that
the owners forego that element of the compensation.
- BTC /
BOTAŞ’ fundamental basis for compensation remains ownership
of land, not impact on livelihoods. The FFM visited two villages
with significant amounts of rented land. In both cases, absentee
landowners had returned to the villages to claim the compensation
payment, leaving nothing for the tenants. Perhaps this is unsurprising:
given that the compensation levels for the land itself have been
found to be well below the land’s true value, landowners are likely
to want to keep anything they get offered, in order to minimise
their losses.
- Many tenants
are not in a position to ask their landlords for written agreements
on compensation, due to imbalances of power in some cases, and
cultural or family and friendship constraints in others. The
villagers the FFM met had heard nothing of BTC’s proposed mechanism
for compensating tenants, and were even surprised when the FFM
suggested it. "Of course, these people cannot ask their landlords!"
The
RAP states rather optimistically that "local traditions are
strong and are likely to protect the tenants’ rights". The
FFM found no evidence to support this assertion.
3.3
OTHER LOSSES ASSOCIATED WITH PROJECT
The
FFM heard evidence of concerns over two general forms of damage
for which villagers feared they would not be compensated: immediate
damage done to land outside the 28-metre pipeline corridor during
construction; and long-term losses due to opportunities that would
have to be foregone due to restriction on land use.
Immediate
Losses incurred during Construction
The
RAP acknowledges that, "During construction of the pipeline
and related infrastructure there may be damage to land, assets and
income of people not involved in the expropriation and compensation
process," and resolves that, "Additional measures will
be taken to ensure that the users of affected land and assets who
may not be owners are directly and adequately compensated."
However, while the FFM spoke to several people and Muhtars who were
concerned about this issue, in no case had compensation for this
even been discussed by BTC / BOTAŞ, let alone agreed.
In
relation to damage to infrastructure, the RAP states that BTC /
BOTAŞ "will ensure that all potentially affected infrastructures
are identified prior to the start of construction and instruct the
contractors to avoid any damage." However, it does not accept
or assign liability for accidental damage, nor propose remediation
or repair of unavoidable damage, such as wear on roads due to the
passage of heavy machinery. This echoes complaints heard by the
FFM in several villages that damage caused to roads and other infrastructure
during the building of the East Anatolian gas pipeline was neither
properly repaired nor compensated for.
Many
villages – even those who were broadly satisfied with the compensation
for the land directly used by the pipeline – expressed concern that
the damage done by construction would extend beyond the 28-metre
strip, and that they would not be compensated for this.
The
only Muhtar whom the FFM found to be broadly happy with the direct
compensation arrangements for the 28-metre corridor itself
nonetheless remained seriously concerned about damage to
fields outside the construction corridor. He knew that in theory
drivers should use the corridor, but was worried that subcontractors
(such as Alarko, which also built the East Anatolian Natural Gas
Pipeline [NGP], and left enormous damage in this process) would
take short cuts. BOTAŞ had told him that it would police the
subcontractors on this issue, but that BOTAŞ itself declined
to take legal responsibility for it. The Muhtar said that the only
method of redress this left open to villagers whose fields and crops
were damaged would be to sue the subcontractor in court – but that
legal costs would exceed the compensation they were suing for, so
no-one would use this recourse.
One
village also anticipated that there would be damage to common land,
and to community assets such as tracks and paths. The villagers
said that when NGP was built, BOTAŞ only compensated main roads
and not tracks; this time BTC / BOTAŞ had not even offered
that.
In
the case of bisected pasture and grazing lands, the RAP claims that,
"passageways will be created … to allow passage from one side
of the pasture to the other, thus avoiding adverse impacts on animal
feeding patterns". While this measure – if applied – would
mitigate the impact, it is wrong to say that it would avoid the
impact, as noise, activity and bisection would clearly each still
disrupt feeding patterns.
Long-term
Losses due to Future Restrictions
One
village – which did not express a view on the fairness of the compensation
for the corridor itself – was unhappy that the value of fields bisected
by the pipeline would be reduced by more than just the proportion
of land lost since these fields would take much longer to plough,
because of the pipeline cutting across the middle. BTC / BOTAŞ
has not offered compensation for this lost value.
In
addition, there are concerns over future restrictions on building
houses. According to the RAP, the BTC pipeline is classified
by the Turkish Ministry of Health as a Non-hygienic Establishment.
Under Turkish health law, the construction of houses is therefore
prohibited within seven metres of the pipeline. Many international
standards recommend a much greater distance, for safety reasons.
However, although people are restricted from building houses, no
compensation is given for this restriction in the use of their land,
outside the eight-metre expropriation corridor.
Turkish
Expropriation Law states that if landowners apply for it, BOTAŞ
should also expropriate (and hence compensate for) any land that
would not be available for living on. Those interviewed by the FFM
appeared to be unaware of this requirement on BOTAŞ; as a result,
they will lose the right to build on this land, with no compensation.
The
Mission notes that the project’s failure to address the impacts
on land value beyond the immediate expropriated portion puts it
in violation of OD 4.30, which requires: "establishing criteria
for determining the resettlement eligibility of affected households,
e.g., households that have only partially lost their assets but
are no longer economically viable should be entitled to full resettlement".
3.4
FAILURE TO PROTECT LIVELIHOODS OF AFFECTED PEOPLE
This
report has outlined above many of the specific failings of the RAP,
both in design and in implementation. However, on top of these,
there are two more fundamental problems with BTC’s very restricted
approach to what constitutes compensation: first, that the compensation
regime focuses on assets rather than incomes, and second, that compensation
is only considered in cash, rather than in terms of replacement
of lost resources. In the FFM’s view, these two flaws will necessarily
render many affected people worse off as a result of the project
rather than better off or with their livelihood restored.
At
times, the RAP makes reference to compensating lost income – for
example, "the loss of income to other users of public lands
will also be recognised and compensated"; "[agricultural
landowners] will be compensated both for land that is permanently
and temporarily acquired on the basis of discounted net income."
However, the compensation procedures, as explained in the RAP and
as confirmed by the FFM, focuses almost entirely on compensating
assets. This is particularly clear, for example, in the case of
tenants (see above).
The
FFM is concerned that in seeking a bureaucratically smooth procedure
for compensation, BTC / BOTAŞ has adopted a legalistic approach
that fails to take account of the subtleties and nuances of customary
land ownership and use. In particular, property rights take
precedence over customary rights. Not only does this approach encourage
unfair valuation of assets, as outlined above, it impacts disproportionately
on those who use - but do not own -land. The latter are generally
the poorest and most disadvantaged groups within communities.
For
example, the Mission was told of one case where a widow who used
the land registered in the name of her dead husband was being denied
compensation, which was instead being paid to inheritors who do
not use the land. In another case, eight inheritors of a portion
of land were compensated equally, even though only one of those
eight actually used the land – and so stood to suffer far more than
the others. In these cases, livelihoods are damaged or lost without
compensation.
In
the FFM’s view, the principal aim of the RAP should be to address
the loss of livelihoods, not just assets. Indeed, the current emphasis
on compensating lost assets rather than lost income violates the
guidance of OD 4.30, whose Clause 16 states: "Vulnerable groups
at particular risk are indigenous people, the landless and semi-landless,
and households headed by females who, though displaced, may not
be protected through national land compensation legislation. The
resettlement plan must include land allocation or culturally acceptable
alternative income-earning strategies to protect the livelihood
of these people" (emphasis added).
The
principles set out in the EIA state that project-affected people
should at least be no worse off as a result of the project. Even
if the value of compensation awarded were genuinely fair, the project
fails to recognise the difference in utility of cash versus land
– this, despite recognising that the majority of livelihood along
the route is land-based. Even if the cash payment were high enough
to allow replacement purchase of land (which the FFM’s findings
above show that it has in general not been), incomes are not reinstated
unless there is land available to buy, of suitable quality, and
near the original land that has been lost. It seems that the project
has made no effort to ensure that affected people are able to replace
their earning resources.
The
World Bank’s OD 4.30 (Involuntary Resettlement) is clear on this
point. Clause 4 states that, "Experience indicates that cash
compensation alone is normally inadequate.... Preference should
be given to land-based resettlement strategies for people dislocated
from agricultural settings. If suitable land is unavailable, non-land-based
strategies built around opportunities for employment or self-employment
may be used." This is repeated in Clause 13: "The Bank
encourages "land for land" approaches, providing replacement
land at least equivalent to the lost land." The FFM therefore
recommends that alternatives to cash should be made available in
order to give those affected by the project the choice of receiving
replacement land.
3.5
INADEQUATE CONSULTATION WITH NGOs
It
is worth also noting that BTC and BOTAŞ could have both ironed
out and resolved problems in the RAP, and facilitated local understanding
of the mechanisms, by working to a greater degree with NGOs. Indeed,
the principles of transparency would suggest that the RAP should
have been disclosed to NGOs in a timely manner. However, the RAP,
which is dated November 2002 was not in fact distributed to international
NGOs until February 2003, when it was first put on the caspiandevelopmentandexport.com
website. Even then, it was taken down after a few days, and only
reinstated when NGOs insisted. The NGOs participating in the FFM
had been asking BP for a copy of the RAP since autumn 2002, and
the company had promised to send a copy as soon as it was completed.
As a result of this delay, NGOs were only able to apprehend the
problems and issues in the RAP at a stage when most of it had already
been implemented – which was too late for constructive suggestions
to be made to influence that implementation.
3.6
CONCLUSIONS
The
FFM finds a wide gulf between the aspirations and commitments of
the RAP on paper and the practice on the ground.
The
FFM finds implementation of the RAP to be in potential violation
of both Turkish law and the World Bank Group/IFC guidelines specified
in the HGA. The FFM is therefore deeply concerned that the expropriation
process is already under way and calls on the BTC Co. and the Turkish
authorities to suspend the land acquisition process until the expropriation
procedure is put in order.
Section
4
PROJECT
IMPACTS ON MINORITY AND DISADVANTAGED GROUPS
The
BTC pipeline passes through a number of areas with significant ethnic
and religious minorities. In Turkey,
these minorities include Alevis, Çerkez and Kurds. Although
the BTC Consortium has committed itself to ensuring that the BTC
project conforms to some relevant World
Bank group/IFC standards, it has declined to apply the World Bank’s
Operational Directive 4.20, Indigenous Peoples, the only directive
specifically aimed at safeguarding the interests of minority groups.
In this, BTC Co has been supported by the International Finance
Corporation, which argues that OD 4.20 is not applicable, and that
a "vulnerable groups" approach (currently being developed
by the World Bank) is more appropriate. In line with this position,
the Resettlement Action Plan (RAP) sets out the project’s approach
to ethnic minority issues in an Appendix entitled "Vulnerable
Groups in the Context of BTC Project".
This
section reviews the controversy over the applicability of OD 4.20
to the BTC project. It sets out the provisions of OD 4.20 with regard
to ethnic minorities and details the IFC’s grounds for arguing that
OD 4.20 is inapplicable to Turkey’s Kurdish minority and hence to
the BTC project. It then reviews the vulnerable groups approach
adopted by the project developers. Finally, it presents the Mission’s
own findings with regard to ethnic minorities and disadvantaged
groups.
The
FFM rejects the view that OD 4.20 does not apply to the BTC project.
It finds that Turkey’s Kurdish minority meets every one of the criteria
that OD 4.20 uses to identify the groups it is intended to safeguard.
Moreover, the FFM is deeply concerned that the "vulnerable
groups" approach adopted by the project developers fails to
protect the interests of ethnic and religious
minorities in the region and, more serious still, could exacerbate
the problems they face. Its arguments are set out below.
4.1 THE
APPLICATION OF OD 4.20 TO TURKEY’S KURDISH MINORITY
- OD 4.20
and Ethnic Minorities
The
World Bank (and hence IFC) has a safeguard measure for the
protection of indigenous ethnic minorities: Operational Directive
OD 4.20 (Indigenous Peoples). This Directive aims to "(a)
ensure that indigenous people benefit from development projects,
and (b) avoid or mitigate potentially adverse effects on indigenous
people caused by Bank-assisted activities".
Although
it notes that no rigid single definition of groups to which
it should apply would be appropriate, the Directive states
that these groups can be identified "by the presence
in varying degrees of the following characteristics:
(a)
a close attachment to ancestral territories and to the natural
resources in these areas;
(b) self-identification and identification by others as members
of a distinct cultural group;
(c) an indigenous language, often different from the national
language;
(d) presence of customary social and political institutions;
and
(e) primarily subsistence-oriented production."
- The Kurds
and OD 4.20
The
IFC has argued that OD 4.20 does not apply in the case of BTC. They
argue that certain of these characteristics do not apply in the
case of project-affected Kurds. In particular, they argue that Kurdish
communities are not:
"i)
primarily involved with subsistence orientated production;
ii)
reliant/dependent on local natural resources."
In
listing these specific objections, the IFC seems to therefore implicitly
acknowledge that the Kurds are indeed identified by themselves and
others as members of a distinct cultural group; do have an indigenous
language that is different from the national language; and also
possess customary social and political institutions. Likewise, the
IFC also appears to accept that Kurdish groups have an attachment
to ancestral territories.
This
in itself is powerful evidence that OD 4.20 should be applied to
the Kurds. Given that the Directive itself says that these characteristics
should not all be applied rigidly, but judged by their presence
in varying degrees, the FFM argues strongly that the clear satisfaction
of three and a half out of five conditions is itself a strong argument
for applying the Directive in this case.
However,
the FFM does not accept that the Kurds are neither primarily involved
with subsistence-orientated production nor reliant on local natural
resources. As already noted, because of state policy towards the
Kurds there is a dearth of sociological research on eastern Turkey,
particularly the north-east due to its isolation, difficult weather
conditions and relative lack of political organisation. Nonetheless,
there is plenty of evidence available to dispute these claims.
The two claims
are fairly similar, in that they claim that the Kurds are no longer
an agricultural society and so are no longer reliant on crop and
animal production. This simply is not true: the Kurdish regions
of Turkey are still almost entirely reliant on agriculture for employment.
They generate approximately 15% of total cereal production in Turkey,
as well as animal meat and products (although these amounts are
considerably down from previous level due to the village clearances
of the 1990’s). The Turkish government’s GAP Authority recently
surveyed five provinces in the south-east, which although not on
the pipeline route are predominantly Kurdish areas socio-economically
similar to the areas on the pipeline route with substantial Kurdish
populations. It acknowledges: "According to the findings of
the field survey, 48% of all households interviewed in the area
make their subsistence primarily on crop farming. This is followed
by paid agricultural labour and non-agricultural seasonal employment
for wage. Livestock farming comes to the fore as the secondary or
tertiary source of income….The labour required in agricultural production
is provided solely by household members in 73% of households. Those
who hire additional labour have a share of 18%."
There
has been a considerable move from a land-based peasantry to a landless
proletariat in the Kurdish regions over the last few decades, largely
for political rather than economic reasons: disruption due to war
twinned with failure to reform the large landholdings still held
by major landlords and tribal leaders have forced many people to
go to the cities or work as day labourers. Since there are few major
industries or employers in the villages along the pipeline route,
those villages that remain would by default be subsistence farmers,
also reliant on remittances from relatives in the big cities or
in Europe.
In
terms of relationship to the land, David McDowall, the acknowledged
UK expert on Kurdish affairs, says in A Modern History of the
Kurds that, "Almost every tribe or tribal section [the
fundamental community unit in the Kurdish regions] also possesses
a strong sense of territorial identity alongside ideas of ancestry.
This is primarily to do with any settled villages and recognised
pasturages a tribe uses." Many Kurdish communities also have
pantheistic belief systems that recognise specific sites, mountains
and streams as holy, and thus conduct a spiritual as well as socio-economic
relationship with the land.
On
top of these considerations, there are a number of other criteria
in OD 4.20 which clearly apply to the Kurds, including:
- Clause
2, which prescribes "special action…where Bank investment
affects indigenous peoples, tribes, ethnic minorities or other
groups whose social and economic status restricts their capacity
to assert their interests and rights in land and other productive
resources." As shown throughout this report, particularly
above and in section 1, the Kurds qualify under every one of
these definitions.
- Clause
3, which states that the Directive applies to "social groups
with a social and cultural identity distinct from the dominant
society that makes them vulnerable to being disadvantaged in
the development process". This clearly includes the Kurds.
- Clause
5 states that "indigenous people are commonly among the
poorest segments of a population. They engage in economic activities
that range from shifting agriculture in or near forests to wage
labour or even small-scale market-oriented activities."
This perfectly describes Kurdish rural economics.
- Isolation
and Marginalisation
The
IFC also argues that the Kurds are not covered by OD 4.20 because
they are not "isolated or disconnected from larger socio-economic
structures of the area." It stresses the importance of achieving
the right balance between "insulating" and "acculturating"
minority groups, and of not risking further marginalising them by
denying them the benefits of the pipeline.
The
IFC’s preoccupation with striking a balance between "insulating"
and "acculturating" minority groups reflects a limited
view of ethnic minorities and indigenous peoples that appears to
be rooted in the reductive archetype of the rainforest tribe completely
cut off from all communication with the outside world. In the FFM’s
view, this is an unjustifiably limited application of OD 4.20, which
would preclude its application from a wide array of situations where
it is essential. In some senses, the situation for the Kurds is
worse than a simplistic polarity of being "in" or "out"
of mainstream society: they have regular interaction with the Turkish
majority, but are isolated and cut off from the benefits and rewards
of that wider society. Some of the ways in which they are sociologically
isolated include:
- Political
discrimination: the repeated violation of the rights of Kurdish
political parties and their members and representatives (see section
1). The Turkish political system is weighted so that even though
over 2 million people voted for the pro-Kurdish party DEHAP, it
has not a single Member of Parliament, effectively disenfranchising
the Kurds.
- Human rights
violations: instances of torture, heavily concentrated on the
Kurdish population, have actually increased for the past
several years, despite EU scrutiny of Turkey’s human rights record.
Dozens of Kurdish people disappear or are extra-judicially killed
each year.
- Displacement:
during the course of the 1990s, between three and four million
Kurds were displaced from their heartlands in southeast Turkey
as a result of a systematic campaign of village destructions undertaken
by the Turkish military, supposedly in order to eliminate the
support base of the rebel Kurdistan Workers’ Party (PKK). Around
5,000 settlements were destroyed, and wide swathes of rural areas
remain virtually empty due to the state’s reluctance to allow
displaced people to return home. Many Kurds have alleged that
village destructions were part of a long-standing central policy
of forcing Kurdish migration from the southeast to facilitate
the assimilation of the Kurds into mainstream Turkish society,
a policy that also includes the siting of major dam and infrastructure
projects in the region.
- Cultural
discrimination: the Kurdish language was banned outright in Turkey
until 1991. The Harmonisation Laws of August 2002, supposedly
liberalising the use of Kurdish in teaching and broadcasting,
have proved hollow: Kurdish broadcasting is allowed on state TV
for a mere two hours per week. Prosecutions and long jail sentences
still regularly occur for giving children Kurdish names, singing
or playing tapes of Kurdish songs and using Kurdish spelling on
posters.
- Economic
neglect: Mayors of towns in eastern Turkey, particularly in the
Kurdish regions, regularly report that their budgets are cut to
1 or 2% of what is required to pay salaries and make local investments,
as part of a co-ordinated central policy to impoverish the regions
and force further economic migration to the big cities. Many public
officials have not been paid for months or even years. Per capita
income in the Kurdish regions is less than a quarter of that in
some of the wealthier western parts of Turkey.
In
the FFM’s view, this constitutes overwhelming evidence of both the
need for and the applicability of OD 4.20 to the Kurds in the BTC
project.
4.2 "VULNERABLE
GROUPS" – A FLAWED APPROACH?
In
refusing to apply OD 4.20, the IFC has argued that the World Bank’s
Indigenous policy is out of date, and that "the World Bank
is looking at reworking the Indigenous Peoples policy as a vulnerable
groups policy". Yet this vulnerable groups policy is not
yet written, leading to great concern that as construction on the
BTC project begins, the failure of BP, BTC Co and the IFC to apply
OD 4.20 effectively leaves no protection mechanism for vulnerable
people affected by the pipeline. In the FFM’s view, this is entirely
unacceptable, and in violation of both the spirit and the form of
the IFC’s own safeguards. In effect, the Bank’s current, official
policy is being jettisoned in favour of one that does not exist.
IFC
also argues that in the context of BTC, it makes more sense to apply
a vulnerable groups type of approach rather than ethnic minorities
or indigenous people, as there are many vulnerable groups, not just
ethnic minorities like the Kurds (for example seasonal herders and
local fishermen). While it is true that there are other groups that
need to be protected, this is not an argument for not applying existing
available protections to the Kurds.
Moreover,
the FFM notes that in the case of involuntary resettlement, BTC
was entirely prepared to apply the old World Bank Operational Directive
4.30, rather than the newer Operational Policy 4.12 on Involuntary
Resettlement. The RAP argues that, "The project will apply
4.30 for the life of the project, since project discussions started
while OD 4.30 was the guiding document for the World Bank Group".
Given that the IFC has begun to move away from OD 4.20 much more
recently than OD 4.30, and therefore OD 4.20 was the "guiding
document" for BTC on vulnerable groups for considerably longer
than OD 4.30 applied to involuntary resettlement, the FFM finds
no justification for BTC and the IFC’s refusal to apply OD 4.20
to fulfil its responsibilities for the protection of vulnerable
groups. The FFM therefore urges the immediate application of OD
4.20 to the BTC project, and considers that the project planners
will have failed to meet their obligations to affected people until
they do so.
4.2.1 Deficiencies
in Project Policy
As
far as the impact of BTC on vulnerable groups such as ethnic and
religious minorities, women, the poor or landless and the elderly
is concerned, the project documents are a classic instance of "the
dog that didn’t bark". The Environmental Impact Assessment
(EIA) does not address the particular impacts of the BTC pipeline
on vulnerable groups. BTC has often said that many of the broader
‘contextual’ issues would be dealt with in the project’s Regional
Review. Yet although this document
has not yet (by mid-April 2003) been released, the indications are
that it will not address these issues. Indeed,
the remit of the Regional Review summary specifically notes that,
"The issues covered in this Review are complex and controversial,
and in many respects outside the control of the projects. Many cannot
be addressed directly by investors undertaking a commercial project.
Many are predominantly, if not exclusively, the domain of sovereign
governments."
The
only significant analysis of the impact of the project on vulnerable
groups in the project documents is in an appendix to the Resettlement
Action Plan (RAP), "Annex 4.6: Vulnerable Groups in the Context
of BTC Project". The FFM believes this appendix to be fundamentally
flawed.
These
flaws are both methodological and conceptual. The methodological
brief of the Annex is clear. "The BTC Project identified vulnerable
groups as well as other project-affected peoples (PAPs) through
the socio-economic surveys undertaken separately for the EIA and
the RAP. Furthermore, the project engaged those groups through a
series of comprehensive consultation and disclosure processes developed
for the Project with the support of international and local SIA
experts."
As
documented in Sections 1 and 2, those consultation processes were
inevitably inadequate due to the BTC consortium’s failure to acknowledge
or take account of the political climate of north-east Turkey, which
as the FFM both saw and experienced is one in which freedom of speech
and opportunities for dissent are severely repressed, particularly
for minority groups such as the Kurds. This failure also renders
the evaluating tools of the project documents, which are primarily
economic and linguistic, deeply inadequate.
The
socio-economic surveys of the project consider the impact of the
pipeline on vulnerable groups only in relation to land expropriation,
without taking into account the social context in which these groups
live. Even within land expropriation issues, the RAP ignores basic
social realities regarding the position of women, ethnic inter-relations,
religious tensions etc. For example, there is no mention of the
difficulties of genuine consultation or negotiation, given the marginalised
and often silenced position of minority groups. As such, the project
is completely at odds with World Bank guidelines on how to deal
with vulnerable groups: "Vulnerability is always contextual,
and must be assessed in the context of a specific situation and
time".
Instead,
the RAP adopts a simplistic, bureaucratic procedure of carrying
out a demographic survey, analysing the income, land ownership and
access to infrastructure such as roads. Finding no substantial statistical
differences between the groups so analysed, the RAP concludes that
there will be no difference in the impact on those groups. It is
difficult to overstate the naivety – or perhaps disingenuousness
– of this approach.
The
fundamental methodological flaw in the rap is that it relies on
narrow, tautological premises derived almost solely from economic
indicators. It is no surprise that, having chosen to ignore the
social and political realities that are the real indicators of group
and individual vulnerability in Turkey, in favour of cherry-picking
a constricted range of economic indicators, that the rap then concludes
that there is little to worry about. BP’s / BTC Co.’s much-vaunted
"non-discriminatory" policy precisely fails those who
are being discriminated against.
The
basic premise of any attempt to work out what "specific vulnerabilities",
as the Annex calls them, certain groups might face is first and
foremost to understand what makes them vulnerable in the first place.
In the case of the Kurds, their vulnerability comes from a socio-political
environment, and more specifically a long-lasting Turkish state
policy, which leaves them systematically discriminated against.
In the FFM’s view, BTC’s reliance on economic methodology has left
it unable to scrutinise those vulnerabilities that would have become
apparent had social and political indicators also been employed.
The FFM finds the narrowing tautology of the BTC Annex not only
ineffective but also deeply flawed. The FFM therefore recommends
that the project be suspended until a genuine and full analysis
of its impact on vulnerable groups is undertaken, and appropriate
mitigation measures developed.
4.3
ETHNIC MINORITIES - FINDINGS OF THE FFM
Other
sections of this report outline the FFM’s findings on the impacts
on women, the elderly and poorer people, and how they have or have
not been addressed by BTC (see also below, sections 4.4.1 and 4.4.2).
This
section considers the projects impacts on the Kurds. Although the
pipeline route avoids the majority Kurdish south-east of Turkey,
it passes through areas in the north-east where Kurds make up about
30% of the population, and through a number of Kurdish villages.
Kurds were the only ethnic minority members interviewed by the FFM
of March 2003; it remains to be researched in detail how the project
would impact on other ethnic groups.
The
Mission’s findings are summarised below:
- Repression
and lack of freedom of speech in the Kars and Ardahan regions
are such that affected people would not be able to frankly express
their views about the project, as any criticism of the project
would be likely to lead to serious repercussions. This particularly
applies to the minority Kurdish population, which is subjected
to much of the same repression as the communities of the south-east,
but lacks the social solidarity and political cohesion used in
majority Kurdish regions to mitigate the impositions of the state
and military.
- A political
culture in which it is considered normal or even acceptable to
express reservations about state-backed projects is conspicuously
lacking in the north-east. The FFM notes that objections to state
decisions, particularly by Kurds, are often construed by the state
as a "separatist" challenge to its authority.
- Specific
consultation measures fell well short of what would be required
to communicate adequately with the local population. In particular,
in the villages visited by the FFM, public meetings were held
with no project officials present who spoke Kurdish. A significant
proportion of Kurds, especially women and the elderly, do not
speak Turkish. This amounts to systematic discrimination through
language, particularly against women.
4.3.1 Omissions
and Inadequacies in the RAP
The
most significant factors influencing how ethnic minorities will
be impacted are ongoing repression by the state and the military,
lack of freedom of speech and political and social marginalisation.
The RAP however takes virtually no account of these factors, relying
entirely on linguistic as well as economic indicators.
It
was with some shock that the FFM read in the RAP that, "Since
1965, no official data has been collected on ethnicity in Turkey.
It was advised that the baseline survey should use language as a
proxy for ethnicity". This approach is quite simply wrong.
In general ethnographic terms, it is fundamentally at odds with
any common definition of ethnicity, which is usually based on self-identification
or identification by others as an ethnic community. Such use of
language as proxy ignores systematic efforts by states to eradicate
or suppress languages, as well as the political realities of survival
and self-preservation that require minority groups to take on certain
facets of the dominant society, of which language is one of the
most obvious.
Furthermore,
although it is the case that almost all Kurds speak Kurdish, the
empirical method of using language as a proxy is unlikely to be
accurate in other cases where minority groups are smaller or more
assimilated into the Turkish mainstream – such as Cerkez, Georgians
and Armenians.
The RAP’s stated
reasons for using language as a proxy are flawed. They can only
be rooted either in a complete lack of understanding of the socio-political
realities of the region or a degree of disingenuousness unacceptable
in such a major document. The idea that, "villagers themselves
"tend not to want to be identified as inhabiting a ‘Kurdish’
village" when addressed by foreign delegations or representatives
of the state can only be a surprise to those unaware of the intensity
of state repression that any form of self-identification as Kurdish
has attracted in Turkey for decades. It does not, however, have
any bearing on whether people think of themselves as or are Kurds.
Likewise, people will be just as reluctant to inform such delegations
that they speak Kurdish as that they are Kurdish. Thus the BTC policy
of using language as proxy of ethnicity produces no gain.
Similarly, if,
as BTC posits, it is "insensitive" to discuss ethnicity
in Turkey (and none of the members of the FFM have ever found it
to be so), it is because the vulnerabilities attached to ethnicity
in Turkey are by definition, and because of state policy, socio-political
rather than economic in nature.
BTC
Co., however, relies on the aforementioned economic surveys to evaluate
vulnerability. This approach produces conclusions riddled with lacunae.
The analysis of the impact on vulnerable groups in the RAP observes
that, "There is no difference in the potential impacts of land
acquisition between Kurdish speaking and non-Kurdish speaking Turkish
households… What is important however is that both groups lose a
similar percentage of their affected plot to both the 28-metre and
the 8-metre corridor," and hence concludes that "language/ethnic
groups are unlikely to be disadvantaged since there is no difference
in the potential impacts of expropriation and construction activities
between Kurdish-speaking and non-Kurdish speaking Turkish households."
In
other words, despite BTC Co.’s pledge "to understand power
dynamics between various groups when mapping the local population,"
the implementation of the BTC project clearly fails to take into
account the nature of the power dynamics under which minority populations
labour, and the social and political adjustments such groups must
make to accommodate those dynamics.
In
Turkey, however, the failures of this approach go well beyond ineffectiveness.
The Turkish polity is unusual in the intensity and systematic nature
of its persecution of its minority communities, especially the Kurds.
For ideological reasons stemming largely from its history, the Turkish
state’s self-perception revolves around the crux of its "indivisible
integrity", and even insignificant sources of Kurdish cultural
expression are reviled as "separatism". It is precisely
because the Turkish state refused for decades
to acknowledge even the existence of the Kurds, insisting
that they be referred to by euphemisms like "mountain Turks",
that no data has been collected on ethnicity in Turkey.
If
a genuine attempt is to be made by the BTC planners to take account
of the Kurds’ and other minorities’ "specific vulnerabilities",
therefore, the historical context must be acknowledged and taken
into consideration when drawing up provisions for their protection.
Instead, BTC Co, as it has done with security and many other project
provisions, appears to insulate itself from contentious issues by
passing responsibility firmly onto the Turkish state—as epitomised
by the disclaimer that begins the Regional Review.
If
the BTC planners genuinely wish to make provision for a group marginalised
and repressed by the state, they cannot judge their circumstances
by the same criteria as other citizens, nor can they leave that
group’s welfare in the hands of the self-same state. BTC Co.’s oft-repeated
"non-discriminatory approach" inherently fails all those
social groups, like the Kurds, that are systematically discriminated
against.
It
is worth noting that BP and BTC Co have fallen behind even the Turkish
state in its reluctance to acknowledge the Kurds. In its attempt
to facilitate its accession to the EU, Turkey has undertaken something
of a liberalisation of policy towards the Kurds in recent years.
The Harmonisation Laws of August 2002, while amounting to very little
in practice, permit some rights of Kurdish language teaching and
broadcasting, and senior Turkish politicians now refer to the Kurds
by name. BP / BTC Co, in contrast, resort frequently to the formulation
"Kurdish-speaking Turkish people" throughout the vulnerable
groups annex of the RAP, a euphemism that denies the existence of
Kurdish ethnicity.
The
FFM thus rejects the current arrangements for the insulation of
vulnerable groups, particularly the Kurds, against the impacts of
the pipeline as tautological, wholly ineffective and likely to lead
to a worsening rather than improvement of these groups’ position.
It sees no alternative for the IFIs but to adopt a full Moratorium
on the BTC project until such time as ethnic minorities and disadvantaged
groups affected by the project are adequately protected.
4.3.2 Need
for a safeguard measure
BTC
claims in its RAP that, "Kurdish-speaking Turkish households
and other ethnic and religious groups are no more vulnerable than
any other group in the context of the BTC project. As such, the
Project has adopted the approach that all groups should be treated
equally."
The
FFM’s findings show that BTC’s conclusion that there is no distinctive
vulnerability is demonstrably false, and therefore the FFM believes
that the approach of treating all groups in a "non-discriminatory
manner" is entirely inappropriate. It ignores the contextual
background of repression of minorities, especially Kurds, by the
state. In the absence of any specific measure to militate against
this, this situation will cause minorities and disadvantaged groups
to be disproportionately impacted by BTC.
Similarly,
IFC’s argument that the Kurds should not be isolated from project
benefits is misplaced. As this report has shown, the impacts of
the project on Kurdish people are overwhelmingly (and disproportionately,
compared to other project-affected people) negative, especially
in that there seems from the FFM’s findings to be a systematic pattern
of Kurds being substantially underpaid for land and resources they
lose to the project. There are also significant doubts that any
major benefits will accrue from the BTC project to local people,
or indeed to the Turkish state.
IFC
also argues that there are other mechanisms for protecting vulnerable
groups, such as the World Bank group’s policy on Involuntary Resettlement
and BP’s community development plan. This report has outlined how
the policy on Involuntary Resettlement is violated in relation to
its impacts on vulnerable groups (see section 3), and found
that no special treatment has been applied to protect ethnic
minorities.
4.4 WOMEN
AS A DISADVANTAGED GROUP
While
the project EIA assesses the position of women in its social baseline
survey, and proposes targets for consultation of women, it does
not extensively deal with how the pipeline would impact differentially
on women. As with other vulnerable groups, the greatest treatment
of specific impacts on women is in the RAP, focusing therefore on
land expropriation issues.
In
no village did the FFM find any evidence of special treatment to
ensure that women were not adversely affected by the project, whether
in relation to expropriation or more generally.
The
RAP complains that, "Unfortunately women do not always come
forward for consultation meetings". However, in the villages
that it visited, the FFM gathered evidence that suggested that BTC
/ BOTAŞ had not made any effort to contact them, or to make
meetings seem relevant or comprehensible to women. In at least three
of the eight villages surveyed by the FFM, women had not been consulted
at all. The others either did not know whether women had been consulted
or did not comment. In both of the Kurdish villages surveyed, the
FFM was told that many of the women do not speak Turkish, only Kurdish,
and BTC / BOTAŞ did not come with Kurdish speakers. BTC Co.’s
failure to take account of this by providing Kurdish speakers at
meetings amounts to a form of gender disenfranchisement through
language.
The
EIA claims that special meetings for women were held, where it was
necessary to do so. However, none of the villages surveyed had a
separate public meeting just for women.
In
the RAP, BTC acknowledges that often only the male ‘head’ of household
would respond to surveys investigating customary land rights and
usage, thus depriving the women of recognition of their ownership
rights. In the villages it surveyed, the FFM also found that BTC
/ BOTAŞ has not in reality made concrete efforts to compensate
women without titles, even when it is known that they have customary
ownership rights. According to one interviewee, "There are
widows who use the land after their husbands’ deaths. There are
lots of problems, because the land is registered in their husbands’
names. BTC / BOTAŞ told them to go to court to get titles.
This costs a lot, so the women are helpless."
In
another village visited by the FFM, for religious and cultural reasons
women are not allowed to see men other than their families and husbands.
During the months of construction therefore, these women would have
to stay indoors with the curtains drawn. They were not consulted.
Considering this type of case, surprisingly, the EIA seems to see
this state of affairs as an actual advantage: "Many respondents
commented that contact between workers and local women would be
a particular source of offence. The conservative traditions of many
of the settlements will largely prevent this type of interaction,
which is more likely in larger population centres used by workers
on their days off." The EIA seems to use this observation as
an excuse for not applying any mitigation measures against this
problem.
The
EIA also records a concern raised by local people during consultation
that, "Lack of control over the movements of construction workers
(during and after working hours) could result in trespassing and
damage to local land and property. This lack of control could also
result in residents, particularly women, feeling vulnerable to the
behaviour of construction personnel as well as creating a sense
of their privacy being invaded." Although the EIA states that
there will be a Code of Conduct to regulate the behaviour of construction
workers, the 11 points listed in the EIA that will be included in
it do not include any rules relating to behaviour towards local
women. Nor are other mitigation measures proposed. In addition,
there appear to be no specific means of redress where women feel
that their rights have been infringed by construction workers or
the construction itself. The FFM recommends that women are consulted
as to appropriate measures and encouraged to participate in their
design and implementation.
The
RAP states that, "an effort will be made to target women with
some of the community development programs to be financed with the
RAP Fund and Community Investment Programmes." The FFM met
women in two villages, and asked about women in other villages where
it was not possible to talk to women directly. No one had heard
anything about these measures, or indeed of any programmes that
were available for women.
In
conclusion, the FFM finds that efforts outlined in the EIA to specifically
consult women appear scarcely to have been applied in practice.
The EIA sets a target that 40% of its consultees should be women,
but did not report on whether it achieved that target. Perhaps as
a result, BTC has at best a limited picture of how women will be
impacted by the pipeline. On land expropriation and compensation
measures in particular, BTC has sketchily noted some of the difficulties
it faces, problems which in the FFM’s view are far from insurmountable,
yet has made little effort to overcome them.
4.5 RELIGIOUS
GROUPS
The
FFM had limited opportunity to review the impact of the BTC project
on religious groups. However, it notes with considerable concern
that there remain outstanding very serious issues concerning violence
between Alevi and Sunni groups, in particular repression of the
Alevi, especially around the Sivas area.
There
have been reported instances of violence between the communities,
or between the communities and state authorities. For example, near
Sivas, 32 Alevi artists and musicians died in 1992, when the building
in which they were meeting was set on fire by a radical Islamic
sect. In 1996, Alevi villages in Sivas province were displaced by
the Turkish state, and in 1999 there was considerable local controversy
over the alleged disproportionate impact of the East Anatolian Natural
Gas pipeline on Alevi villages in the region.
As
with the Kurds, the BTC EIA neither makes any mention of these background
problems, nor proposes measures to ensure it does not exacerbate
them. As noted above, the FFM eagerly awaits the public release
of the project Regional Review. For now, the FFM notes that the
Alevi are not mentioned in the Executive Summary of the Regional
Review.
In
the discussion of vulnerable groups in Annex 4.6 of the RAP, it
is stated that "these sects [Alevi and Sunni] usually live
side-by-side without discordance". While it is the case that
many communities do contain both Alevi and Sunni living harmoniously,
the FFM is deeply concerned that BTC did not see fit to mention
the exceptions to that harmony, in which extensive violence took
place. As with the ethnic minorities, the FFM is of the view that
the RAP’s analysis of vulnerability of religious groups is simplistic
and overly bureaucratic, looking only at the economic position of
the different groups.
The
FFM was not able to research the current situation in relation to
the Alevi; however it notes with concern that when it asked one
community leader about the situation, he replied that he could not
discuss it in public – suggesting that the issue remains very sensitive.
Given the history of tensions and human rights problems, the
FFM recommends that international financial institutions initiate
an urgent and independent review of the human rights impacts the
BTC project would have on Alevi communities and people.
Section
5
CORRUPTION
ALLEGATIONS
The
FFM’s remit included conducting preliminary investigations into
allegations made in the Turkish press of corruption in the award
of sub-contracts for work on the BTC pipeline. The FFM interviewed
sources who had been following the allegations and is now awaiting
further information. The FFM intends to publish a supplementary
report shortly, detailing the Mission’s findings.
Section 6
SUMMARY
AND RECOMMENDATIONS
6.0 SUMMARY
OF FINDINGS
6.1 Systemic
Problems Undermine Legitimacy of Consultation
Whilst the current
Fact-Finding Mission (FFM) found that the BTC Consortium (BTC Co.)
has taken steps which partially address a number of the concerns
identified by the July 2002 Mission, the FFM nonetheless
found:
- Continuing
violations of international standards on consultation, compensation
and resettlement still characterise the project;
- A pervasive
atmosphere of repression and lack of freedom of speech in the
region precludes dissent about the BTC project;
- The strong
likelihood of the human rights situation in the region being worsened
by the introduction of the pipeline, particularly due to militarisation
via the use of the gendarmerie (Turkey’s military police) as the
main security force.
Specifically,
the FFM found:
- The lack
of freedom of expression in the Kars and Ardahan regions renders
wholly illegitimate the consultation processes which BTC Co. has
carried out. The FFM considers it untenable to suggest that
people subject to the kind of duress which it witnessed and experienced
would
be in a position openly to object to a project of great importance
to the state, being carried out by the state pipeline company.
- The flawed
and inadmissible consultation processes carried out by BTC Co.
have in themselves compounded the atmosphere of human rights repression
in the North-East, by giving a veneer of collective participation
to what is in reality a state-imposed decision on local people.
- The prospect
of a legitimate consultation process being carried out in the
absence of major human rights reforms is unattainable.
- The combination
of the desire of the BTC consortium to insulate itself from the
security issue, the investment of security powers in the Gendarmerie
and the atmosphere of repression and intense surveillance which
characterises large stretches of the pipeline route, make a marked
increase in human rights abuses - both immediately and in the
long-term – highly probable. There are suggestions that the imminence
of the BTC project has worsened the degree of state intrusion
and the repression of dissent.
- Specific
Deficiencies in Consultation and Compensation Procedures
These problems
of social context were compounded by an array of specific deficiencies
in the BTC project, including:
- A number
of apparent conflicts between the Resettlement Action Plan (RAP)
for the project and the Turkish Expropriation Law;
- Fundamental
flaws in both the design and the implementation of crucial project
documents like the Environmental Impact Assessment (EIA) and
the Resettlement Action Plan (RAP), including widespread inadequacies
in consultation of appropriate NGOs and social groups;
- Repeated
suggestions that the BTC Consortium
is not carrying out the process of compensation in the manner
claimed. These failures are generating
growing
anger among affected people;
- The failure
of the project to take sufficient account of the differential
impacts of the pipeline on vulnerable groups, including ethnic
minorities, women and the poor, or to mitigate those problems
appropriately.
The FFM notes
that this catalogue of deficiencies puts the BTC project in potential
conflict with the Host Government Agreement reached between BTC
Co. and the Turkish Government. It also places the project in violation
of a number of the World Bank Group’s mandatory standards, including
OD 4.30 (Involuntary Resettlement), and guidelines.
Specifically,
the FFM found:
- Consultation
and Disclosure of Information Flawed
- Serious flaws
in the process of consultation that should have taken place during
the scoping period for the Environmental Impact Assessment (EIA).
- The review
and approval procedure for the EIA had been truncated, leaving
the Ministry of Environment with insufficient time to comment
prior to approval.
- Consultation
of directly affected people was inadequate: villagers had not
been provided with information on the negative environmental impacts
of the project; the potential benefits of the project were
consistently overstated;
what
information had been provided was too technical; and the information
given regarding the means of redress in case of complaints was
confusing and one-sided.
- Women
were not adequately consulted, were discriminated against by the
choice of language in the consultation process, and, in some instances,
were not consulted at all.
- None of
the bodies, organisations or villages visited by the FFM had been
informed of the existence or nature of the Host Government Agreement
and Intergovernmental Agreement which provide the legal framework
for the project, despite the crucial importance of these agreements
to Turkey, its citizens and the project itself.
The FFM notes
that the generalised failure to ensure proper consultation on the
EIA, the RAP and the HGA is neither in the interests of those affected
nor of the project developers. On the contrary, there is a strong
possibility that the failure to consult will engender resentment
of the project and act against its smooth implementation and future
operation, in addition to incurring reputational risks for the companies
that form the BTC Consortium.
b. Land Expropriation
and Compensation – Legal and Human Rights Concerns
The FFM found
that significant progress had been made towards resolving several
of the issues relating to resettlement identified by a previous
Fact Finding Mission, notably on the issue of compensation for land
users without title. However, such progress does not extend to
the north-eastern section of the pipeline route (Posof to Kars).
Moreover, throughout the pipeline route, the FFM found widespread
evidence of major shortcomings in the design and implementation
of the RAP:
- The RAP’s
provisions on negotiating land prices appear to be in conflict
with the requirements of Turkey’s Expropriation Law, placing the
project in potential breach of the HGA;
- BTC is consistently
underpaying and failing to provide a fair price for land, despite
claims to the contrary. According to villagers interviewed by
the FFM, not a single payment was as high as the budgeted average
in the RAP, and most were about half that level. This is in part
due to a failure to get a measure of the true rather than the
registered market value of land.
- Although
a ‘RAP Fund’ has been set up to compensate those without land
title, in compliance with the requirements of the World Bank Group,
no-one interviewed by the FFM had any knowledge of the Fund. As
a result, those eligible for compensation through the fund – often
the poorest in the community – are not in a position to apply
for compensation. The RAP Fund, in practice rather than theory,
simply does not exist for people in the region;
- Similarly,
it is highly improbable both for practical and cultural reasons
that the majority of tenants will receive any form of compensation.
In any case, as tenants will only be compensated for assets, of
which almost by definition they have very few, rather than loss
of income, the amount of money involved would not be enough to
restore their socio-economic position even if they were able to
obtain it.
- This is part
of a wider phenomenon of BTC’s systematic failure to compensate
for loss of income rather than for immediate assets lost. This
includes failure to compensate for loss of ongoing productivity,
failure to pay the full replacement cost of land and failure to
compensate for economic opportunities foregone and investments
precluded by the pipeline and its construction processes.
- Villagers
interviewed by the FFM suggested that they had been consistently
misinformed about their opportunities for redress if they disagreed
with the compensation figure or process. Some said they had been
told they were not entitled to go to court, others that they could
go, but it would be expensive and time-consuming. Under Turkish
law, the costs of ensuring due process should be born by the expropriating
authority.
- The majority
of the protection mechanisms that BTC has claimed will ensure
that all project-affected people are not negatively impacted by
the project are either unknown to local people, inoperative, ineffective
or are not being applied by BTC staff. It is of particular concern
that BP has claimed credit from IFIs and other potential project
funders for policies which in practice do not exist.
c. Continuing
Lack of Provision for Minority and Disadvantaged Groups
Although the
World Bank Group has a safeguards policy aimed at protecting ethnic
minority (known as OD 4.20), both the BTC Co and the International
Finance Corporation of the World Bank have argued that it does not
apply to the BTC project. The FFM rejects this view. It finds that
Turkey’s Kurdish minority meets every one of the criteria which
OD 4.20 stipulates as defining indigenous groups or necessitating
special protective measures. Moreover, the FFM is deeply concerned
that the "vulnerable groups" approach adopted by the project
developers fails to protect the interests of ethnic minorities in
the region and, more serious still, could exacerbate the problems
they face.
The Mission
also found:
- The most
significant factors influencing how ethnic minorities will be
impacted are ongoing repression by the state and the military,
lack of freedom of speech and political and social marginalisation.
The RAP however takes virtually no account of these factors. The
policy adopted by BTC Co. in relation to ethnic minorities, particularly
the Kurds, takes no account of the socio-political realities that
define vulnerability, and fail to take advantage of Turkey’s legislative
"if not practical" liberalisation of its Kurdish policies
in recent years.
- While the
project EIA assesses the position of women in its social baseline
survey, and proposes targets for consultation of women, it does
not extensively deal with how the pipeline would impact differentially
on women.
- The FFM had
limited opportunity to review the impact of the BTC project on
religious groups. However, it notes with considerable concern
that there remain outstanding very serious issues concerning violence
between Alevi and Sunni groups, in particular repression of the
Alevi, especially around the Sivas area.
6.3 THE
CASE FOR A MORATORIUM
Whilst many
of the deficiencies identified by the FFM (for example, with regard
to levels of compensation) may be remedied by making more funds
available and by taking more time to resolve the outstanding violations
of international standards and potential conflicts with domestic
law, the systemic problems arising from repression in the region
are not amenable to remedial action by either the project developer
or the international financial institutions from which funding for
the project is being sought:
- The World
Bank has no safeguard policies relating to human rights and
therefore no human rights standards that the project must meet
if it is to receive funding. Indeed, the Bank has specifically
argued that its Articles of Agreement, which forbid the Bank
from intervening in the political affairs of client states,
preclude the Bank from adopting any such guidelines since human
rights are inherently "political" issues. Nonetheless,
as Ibrahim Shihata, the former General Counsel of the Bank notes:
"Members’ obligations under the UN Charter prevail over
their other treaty obligations, including their obligations
under the Bank’s Articles of Agreement, by force of an explicit
provision in the UN Charter (Article 103). The Bank itself is
bound, by virtue of its Relationship Agreement with the UN,
to take note of the above-mentioned Charter obligations assumed
by its members …." From this legal experts have concluded
that,
"the Bank is obliged, as is any other subject of the law,
to ensure that it neither undermines the ability of other subjects,
including its members, to faithfully fulfil their international
obligations nor facilitates or assists violation of those obligations."
In effect, the Bank’s inability to act to address the human
rights concerns identified in this report, coupled with its
obligation to ensure that human rights abuses do not flow from
the project should it be involved, points to its withdrawal
until measures have been taken to remedy the concerns raised
as the only viable option open to it.
- The
BTC Consortium is a private company and, whilst the Host Government
Agreement (HGA) it has signed with Turkey gives it considerable
legal powers over those living in the pipeline corridor, it
is not in a position to introduce the necessary policy reforms
that would ensure that Turkish citizens enjoy the freedom of
expression necessary to participate in a proper consultation
on the project or to safeguard their property rights. As
the BTC Consortium itself notes in its own regional review for
the project: "The issues covered in this review are complex
and controversial, and in many respects outside the control
of the projects. Many cannot be addressed directly by investors
undertaking a commercial project. Many are predominantly, if
not exclusively, the domain of sovereign governments."
- The
HGA signed by the project developers and the Government of the
Republic of Turkey specifies that Turkey, not BTC Co, will be
responsible for security. The project developers have therefore
placed a vital arena of operations outside their control. Without
a renegotiation of the HGA, to which all parties must agree,
the project developers therefore have no powers to control the
security provisions and operations for the pipeline.
In such circumstances,
the FFM believes that a Moratorium on appraising, financing and
building the BTC project constitutes the only legitimate means available
to the International Financial Institutions and the project developers
for ensuring that human rights violations do not flow from the project.
As such, it represents the most responsible course of action.
6.3 RECOMMENDATIONS
- An Immediate
Moratorium
BTC
Co and International Financial Institutions should place a moratorium
on the project until it is able to ensure that implementation of
the project is compliant not only with international law and standards
applicable, including those which BTC Co has pledged to apply, but
also with essential human rights practice in project affected areas.
The
FFM further recommends that the resumption of the BTC project should
be conditional on:
- BTC Co obtaining
independent confirmation that the Turkish authorities have taken
appropriate measures to ensure that freedom of expression is a
viable and genuine norm
in project
affected areas. This necessitates a systemic change in practices
of security and respect for human rights in the region, which
can only be instituted over a period of time.
- Turkey being
encouraged to comply demonstrably
with
the obligations which affect all European Union member states,
in order to illustrate its acceptance of EU standards as its application
for EU membership.
- All states
and companies involved in the project affirming their commitment
to best practice, as set out in the OECD, IFC and World Bank guidelines,
and acting in accordance with such practice.
- Those affected
by BTC being substantively
involved
in all stages of the project, including the opportunity within
reason to modify aspects of the design or operation with which
they are discontented or which they see as overly damaging or
unfair. Thorough and sustainable strategies to ensure the participation
of local people must be drawn up prior to recommencement of the
project, in the light of the extreme conditions in the area.
- BTC Co guaranteeing
that compensation for land will be
paid
as a result of independent valuation and through genuine
negotiation
and bargaining between affected people and the companies involved.
- BTC Co giving
an undertaking that an independent body commissioned by an outside
agency (i.e. not directly funded by either the project consortium
or its financiers)
will
monitor all phases of the project, from construction to decommissioning,
and that its recommendations will be implemented.
- BTC Co and
international financial institutions ensuring that all current
irregularities and failings of the project outlined in this report
are appropriately addressed prior to the recommencement of the
project.
b.
Consideration of legal remedies
Several
aspects of the existing proposals threaten to breach domestic and
international law. In the absence of remedial measures to address
the concerns raised in this report, the FFM advises affected parties
to explore the legal remedies available to them. Some of the fora
in which legal redress might be pursued are outlined below:
- Turkish domestic
courts
- The lack
of negotiation when reaching a price for the land is in apparent
breach of Turkish Expropriation law;
- Current conditions
in the region make it unlikely that the requirements of Turkish
law concerning expropriation and compensation will be upheld.
Those affected would, however, have access to the Turkish courts.
- Actions to
review any final decision to proceed would be subject to judicial
review in the Turkish administrative courts.
- Domestic
courts elsewhere
- Any decision
to support the project financially through an arm of government
could be the subject of administrative law review. The grounds
for such a review include the legality of the decision making
process, and might contain issues concerning the potential human
rights violations which flow from the project, including social
and political considerations and environmental concerns. The international
laws, guidelines and standards relating to large-scale projects
such as this will be of key relevance in such proceedings.
- Those companies
which offer support for the project may be vulnerable to action
from their shareholders, on the basis of a breach of company guidelines,
or in view of the likely consequences to the company of proceeding
with a project like this.
- European
Court of Human Rights
Subject to
the exhaustion of domestic remedies, individuals ultimately affected
by the project will have access to the European Court of Human
Rights (ECtHR). Breaches of Article 6 (right to a fair hearing),
8 (right to home and family life), 10 (freedom of expression),
13 (right to an effective remedy), 14 (freedom from discrimination)
and Article 1 of Protocol 1 (right to peaceful enjoyment of possessions)
on the part of Turkey are all likely if the project goes ahead,
and could therefore form the basis of private applications along
the lines of the 403 cases in which the ECtHR had ruled against
Turkey as of February 2003.
|